Elk Unit 4
210 MW generation in Hale, TX · In queue since April 2024 · Proposed COD February 2027
210 MW
Capacity
1
Components
Gas
2y 7m
In Queue
Facility Study
IA Phase
Signed Dec 2025
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Queue → IA
1y 8m
IA → COD
1y 2m
Total Duration
1y 8m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
SS Completed, FIS Completed, IA
Project under construction
Typical: 24–48 months
Proposed COD: 2027-02-28
Projected COD moved
0 times
Feb 2027 → Feb 2027
Net change
0 months
first report to latest
Capacity
210 MW
unchanged in the reports
Latest stage
IA signed
in ERCOT's latest report
Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).
From dated articles. These observations may describe earlier stages or other project phases; see the queue record above for reported filing status.
Cross-source intelligence
Experimental assessment saved at the research date. Predates the Oct 1, 2026 queue source. See the queue record for reported project facts.
Milestones in this assessment
Target interconnection agreement execution date per ERCOT queue
lbnl_queue_snapshotProposed commercial operation date for 210 MW gas facility
lbnl_queue_snapshotResearch sources and reasoning (1 recorded sources)
low confidence at research time
- lbnl_queue_snapshot
Commercial operation date: Only LBNL queue data available with proposed COD of February 2027. No independent news or press releases found to validate or contradict this date.
Developer: LBNL lists Golden Spread Electric Cooperative, Inc. as developer. This appears to be the actual operating entity (a generation and transmission cooperative) rather than a shell LLC, and no contradictory ownership information was found.
Status: LBNL status shows Active with IA Status at Facility Study stage. No news coverage found to indicate construction activity, permitting milestones, or status changes.
About
Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
Elk Unit 4 is a proposed 210 MW gas-fired generation project located in Hale County, Texas. The project, developed by Golden Spread Electric Cooperative, Inc., is in the ERCOT interconnection queue as entry ERCOT-27INR0181, with a queue entry date of April 9, 2024. The proposed commercial operation date is February 28, 2027. The project's interconnection status is currently in the Facility Study phase.
The Elk Unit 4 project has been the subject of recent news coverage, with five articles related to the industry and development of the project.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- ERCOT queue source as of: Oct 1, 2026.
- Queue history observations through: Sep 2026.
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Hale
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Golden Spread Electric Cooperative, Inc.
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
141607 AEEC_5
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_WEST
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Last updated 2026-07-11
View all articlesUnit 4
Data-driven briefing on Unit 4 — fleet, generation, financial, and news signals.
Elk Unit 4
Data-driven briefing on Elk Unit 4 — fleet, generation, financial, and news signals.
Cooper
Data-driven briefing on Cooper — fleet, generation, financial, and news signals.
ATI
Data-driven briefing on ATI — fleet, generation, financial, and news signals.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.