Cielo Vista Solar
503.34 MW hybrid in Duval, TX · In queue since April 2025 · Proposed COD March 2029
503.34 MW
Capacity
1
Components
Solar
1y 7m
In Queue
Facility Study
IA Phase
COD target: 2029
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Total Duration
3y 11m
Interconnection request submitted to ISO/RTO
SS Completed, FIS Started, No IA
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2029-03-30
Projected COD moved
1 time
Jun 2028 → Mar 2029
Net change
+9 months
first report to latest
Capacity
503 MW
unchanged in the reports
Latest stage
Screening started
in ERCOT's latest report
Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).
Cross-source intelligence
Experimental assessment saved at the research date. See the queue record for reported project facts.
Milestones in this assessment
Duval County Commissioners Court approved a Chapter 312 tax abatement and reinvestment zone (1,500 acres) requested by Cielo Vista Storage, Solar and Power LLCs.
co.duval.tx.usResearch sources and reasoning (5 recorded sources)
low confidence at research time
- co.duval.tx.us/upload/page/11362/20260416_Notice%20of%20intention%20-Cielo%20Vista.pdf
- cleanview.co/power-projects/planned/solar-farms/texas/27INR0150/cielo-vista-solar
- infrasure.ai/project/ercot-27inr0150-cielo-vista-solar
- kiiitv.com/article/news/local/duval-county-solar-project-water-concerns/503-5dd06b70-0f97-4fa6-a570-6ab3262e8070
- infrasure.ai/project/ercot-29inr0115-cielo-vista-storage
Commercial operation date: Only the LBNL/ERCOT filing gives a solar COD (2029-03-30). Cleanview's 'Expected online 2029' is consistent with it but appears to be derived from the queue data, so there is no independent post-LBNL signal. The sister storage project (29INR0115) targets June 2028, but that is a separate queue entry.
Developer: The county tax-abatement notice names Cielo Vista Storage, LLC, Cielo Vista Solar LLC and Cielo Vista Power LLC as applicants, which are all project shell entities. No sponsor or parent operating company is identified in any source.
Status: LBNL shows active status at Facility Study with no IA date. County abatement approval and local public hearings confirm ongoing development, with no sign of withdrawal or construction start.
About
Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
Cielo Vista Solar, LLC is proposing a 503.34 MW solar photovoltaic generation project in Duval County, Texas. The project, named Cielo Vista Solar, is currently active in the ERCOT interconnection queue as entry ERCOT-27INR0150, with a queue entry date of April 21, 2025. The proposed commercial operation date is June 30, 2028.
The point of interconnection for the proposed project is Tap 345kV Bus #5901 Miguel5 - Bus #80079 Cruce7A Ckt 1. The project is listed as active in the ERCOT queue.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- ERCOT queue source as of: Oct 1, 2026.
- Queue history observations through: Sep 2026.
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Duval
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Cielo Vista Solar, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 345kV Bus #5901 Miguel5 - Bus #80079 Cruce7A Ckt 1
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_SOUTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
TOCE TX BESS 2
Cross-dimensional entity briefing with KPIs, news intelligence, and fleet analysis.
Solar queue pipeline by status
Data tables and metrics from the InfraSure database.
Texas energy overview
Summary analysis with parallel narrative sections and visualizations.
State-by-state breakdown for ERCOT (Texas)
Summary analysis with parallel narrative sections and visualizations.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.