Cielo Vista Storage (ERCOT-29INR0115) — Project Summary

Queue ID
ERCOT-29INR0115
Capacity
310.8 MW
Technology
Solar+Battery
Status
active
Location
Duval, TX
Region
ERCOT
Developer
Cielo Vista Storage, LLC
IA Status
Facility Study

Cielo Vista Storage

ERCOT-29INR0115BetaActiveBatteryBatteryERCOTLBNL + Live

310.8 MW generation in Duval, TX · In queue since April 2025 · Proposed COD March 2029

BA: ERCOISO/RTO: ERCOTNERC: TRERC: ERCOT

310.8 MW

Capacity

1

Components

Battery

1y 7m

In Queue

Facility Study

IA Phase

COD target: 2029

Asset Intelligence Map

One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.

5 live dimensions
4 decision models

Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.

Structured from the current asset record; empty data branches are omitted.Locked nodes are InfraSure decision models; no simulated values shown.
Interconnection

Total Duration

3y 11m

Facilities Study50%
Queue EntryApr 21, 2025

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

SS Completed, FIS Started, No IA

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2029-03-30

Queue history
29INR0115 · 19 monthly ERCOT reports, Mar 2025 – Sep 2026

Projected COD moved

1 time

Jun 2028 → Mar 2029

Net change

+9 months

first report to latest

Capacity

311 MW

unchanged in the reports

Latest stage

Screening started

in ERCOT's latest report

Projected COD in each reportDue now (report date = COD)Milestone first reported
Screening study startedApr 21, 2025

Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).

Cross-source intelligence

Saved research · Beta
Researched Oct 25, 2026

Experimental assessment saved at the research date. Research and queue COD differ; this comparison does not confirm either date. See the queue record for reported project facts.

Research COD
Jun 30, 2028
Differs from queue: Mar 30, 2029
Developer in saved assessment
Cielo Vista Storage, LLC
From queue filing
Status at research time
Active
Active in the ERCOT queue at the Facility Study phase with no IA executed. Duval County approved a tax abatement on 2026-04-13, which suggests the project is progressing locally.
Financing
Not recorded

Milestones in this assessment

Permit approvedApr 13, 2026Latest in this assessment

Duval County Commissioners Court approved a Chapter 312 tax abatement and reinvestment zone for Cielo Vista Storage, Solar and Power LLCs. This is a local incentive approval, not a construction permit. The county listing describes a 400 MW storage facility with an estimated cost of $146.5M.

co.duval.tx.us
Research sources and reasoning (5 recorded sources)

low confidence at research time

  1. infrasure.ai/project/ercot-29inr0115-cielo-vista-storage
  2. cleanview.co/planned-battery-projects/TX/29INR0115/cielo-vista-storage
  3. co.duval.tx.us/upload/page/11362/20260416_Notice%20of%20intention%20-Cielo%20Vista.pdf
  4. co.duval.tx.us/upload/page/11369/20260413_CommCrtAgenda.pdf
  5. newtools.cira.state.tx.us/page/duval.Public.Information

Commercial operation date: Infrasure reports a 'Proposed COD: 2028-06-30' and Cleanview says 'expected to come online in June 2028', against the LBNL date of 2029-03-30, a gap of about 9 months. Both aggregators appear to derive from the ERCOT queue rather than a developer announcement, and a second Cleanview page still says 2029, so this is a weak signal.

Developer: County tax-abatement documents name Cielo Vista Storage, LLC, together with affiliates Cielo Vista Solar LLC and Cielo Vista Power LLC, as applicants. No parent or operating company is identified in any source, so the LBNL filing entity is kept.

Status: LBNL and the aggregators all list the project as active. The April 2026 county abatement approval is consistent with continued development, and no source shows construction or withdrawal.

About

Saved background

Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source

Figures and claims below reflect the saved summary. See the queue record for reported project facts.

Cielo Vista Storage, LLC is proposing a 310.8 MW hybrid battery storage project in Duval County, Texas. The project, identified as ERCOT-29INR0115 in the ERCOT interconnection queue, entered the queue on April 21, 2025, with a proposed commercial operation date of June 30, 2028. The point of interconnection is Tap 345kV Bus #5901 Miguel5 - Bus #80079 Cruce7A Ckt 1.

The Cielo Vista Storage project is currently listed as active in the ERCOT queue. The project consists of battery energy storage, and is classified as "Other" under technology detail. The developer is listed as Cielo Vista Storage, LLC.

Summary provenance

Summary generated Apr 10, 2026 (UTC).

Source dates used by this summary were not recorded.

Dates in the current asset record

These may postdate the saved summary; they do not establish which inputs it used.

  • ERCOT queue source as of: Oct 1, 2026.
  • Queue history observations through: Sep 2026.
Development Risk

Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.

Available on the InfraSure platform

See the full development-risk decomposition for this project.

P(COD by stated date)
Withdrawal probability vs cohort
IA cluster risk
Project Details

State

TX

County

Duval

Grid Region

ERCOT (Texas)

Market

ISO/RTO Member

Developer

Cielo Vista Storage, LLC

Utility

—

Entity

ERCOT

Service Type

—

Point of Interconnection

Tap 345kV Bus #5901 Miguel5 - Bus #80079 Cruce7A Ckt 1

Data Source

LBNL + Live

Risk Analytics

Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.

Available on the InfraSure platform

See the full risk decomposition + scenarios for this project.

Climate hazards (8+)
Generation variability (P10/P50/P90)
Offtake + transmission counterparty
Generation Forecast

Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.

Available on the InfraSure platform

See the full forecast + scenario decomposition for this project.

P50 conditioned on COD
Capacity factor vs cohort
Weather + policy scenarios
Financial Forecast

Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.

Available on the InfraSure platform

See the full revenue + DSCR projection for this project.

Revenue conditioned on COD
Financing close risk
Cohort DSCR comparison
Market Context
Approximate
ISO / RTO
ERCOT
Trading Hub
HB_SOUTH
Hub Confidence
LOW

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No insights available for this project.