Timmerman Power Plant Phase 2 (ERCOT-25INR0503) — Project Summary

Queue ID
ERCOT-25INR0503
Capacity
188.4 MW
Technology
Gas
Status
active
Location
Caldwell, TX
Region
ERCOT
Developer
Lower Colorado River Authority
IA Status
IA Executed

Timmerman Power Plant Phase 2

ERCOT-25INR0503BetaActiveGasERCOTLBNL

188.4 MW generation in Caldwell, TX · In queue since September 2023 · Proposed COD May 2026

BA: ERCOISO/RTO: ERCOTNERC: TRERC: ERCOT

188.4 MW

Capacity

1

Components

Gas

3y 2m

In Queue

IA Executed

IA Phase

Signed Dec 2023

Asset Intelligence Map

One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.

5 live dimensions
4 decision models

Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.

Structured from the current asset record; empty data branches are omitted.Locked nodes are InfraSure decision models; no simulated values shown.
Interconnection

Queue → IA

3 months

IA → COD

2y 5m

Total Duration

3 months

Schedule

6 months past proposed COD

Construction75%
Queue EntrySep 22, 2023

Interconnection request submitted to ISO/RTO

Interconnection Study

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection AgreementDec 28, 2023

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 24–48 months

Commercial Operation

Proposed COD: 2026-05-29

Queue history
25INR0503 · 30 monthly ERCOT reports, Oct 2023 – Mar 2026

Projected COD moved

6 times

Feb 2026 → Apr 2026

Net change

+2 months

first report to latest

Capacity

188 MW

unchanged in the reports

Latest stage

Commercial operation

last listed Mar 2026

Projected COD in each reportDue now (report date = COD)Milestone first reported
Screening study startedSep 22, 2023
Facilities study approvedJun 4, 2025
Interconnection agreement signedDec 28, 2023
Approved for energizationDec 10, 2025
Approved for synchronizationFeb 13, 2026
Approved for commercial operationApr 16, 2026

Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).

Cross-source intelligence

Saved research · Beta
Researched Jun 1, 2026

Experimental assessment saved at the research date. Research and queue COD differ; this comparison does not confirm either date. See the queue record for reported project facts.

Research COD
Apr 2026
Differs from queue: May 29, 2026
Developer in saved assessment
Lower Colorado River Authority
Sources agreed at research time
Status at research time
Online
Online — plant came fully operational April 2026, one month ahead of schedule; received Texas Energy Fund completion bonus grant
Financing
Secured
Texas Energy Fund (TxEF) performance-based completion bonus grant executed by PUCT November 2025; project was part of $5.38B loan program for dispatchable generation

Milestones in this assessment

IA executedDec 28, 2023

Interconnection Agreement executed per LBNL queue data

texasborderbusiness.com
Financing closeNov 2025

PUCT executed first TxEF Completion Bonus Grant agreement for Phase 2

powermag.com
COD targetApr 2026Latest in this assessment

Plant came fully online one month ahead of May 2026 target

texasborderbusiness.com
Research sources and reasoning (4 recorded sources)

high confidence at research time

  1. texasborderbusiness.com/timmerman-power-plant-comes-fully-online-one-month-early/
  2. powermag.com/texas-issues-first-performance-based-grant-under-energy-fund-for-lcras-new-188-mw-rice-peaker/
  3. austinmonitor.com/stories/2024/04/lcra-ups-its-peaker-power/
  4. powermag.com/texas-moves-forward-with-5-38b-in-loans-for-10-gw-of-new-dispatchable-power-projects/

Commercial operation date: Texas Border Business reports the plant 'came fully online one month early' approximately 1 month ago (May 2026), indicating actual COD in April 2026 vs. LBNL's proposed May 29, 2026. This represents early completion rather than delay.

Developer: LBNL filing entity 'Lower Colorado River Authority' matches all press coverage and is the actual operating utility, not a shell LLC. No ownership changes detected.

Status: Texas Border Business and POWER Magazine confirm the 188-MW RICE peaker is now fully operational as of April 2026, with PUCT executing the first TxEF Completion Bonus Grant agreement in November 2025.

About

Saved background

Generated Apr 10, 2026

Figures and claims below reflect the saved summary. See the queue record for reported project facts.

The Uhland Maxwell Expansion is a proposed 188.4 MW gas-fired generation project located in Caldwell County, Texas. The developer is Lower Colorado River Authority. It is interconnected within the ERCOT region under queue ID ERCOT-25INR0503, with a queue entry date of September 22, 2023, and a proposed commercial operation date of April 30, 2026.

The project's Interconnection Agreement (IA) has been executed as of December 28, 2023. The point of interconnection (POI) is the 7041 John Dumas 345kV substation.

Summary provenance

Summary generated Apr 10, 2026 (UTC).

Source dates used by this summary were not recorded.

Dates in the current asset record

These may postdate the saved summary; they do not establish which inputs it used.

  • LBNL queue source as of: Dec 31, 2025.
  • Queue history observations through: Mar 2026.
Development Risk

Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.

Available on the InfraSure platform

See the full development-risk decomposition for this project.

P(COD by stated date)
Financing close probability
EPC + tax-equity counterparty
Project Details

State

TX

County

Caldwell

Grid Region

ERCOT (Texas)

Market

ISO/RTO Member

Developer

Lower Colorado River Authority

Utility

—

Entity

ERCOT

Service Type

—

Point of Interconnection

7041 John Dumas 345kV

Data Source

LBNL

Risk Analytics

Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.

Available on the InfraSure platform

See the full risk decomposition + scenarios for this project.

Climate hazards (8+)
Generation variability (P10/P50/P90)
Offtake + transmission counterparty
Generation Forecast

Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.

Available on the InfraSure platform

See the full forecast + scenario decomposition for this project.

10-year P50 forecast
First-year output estimate
Weather + policy scenarios
Financial Forecast

Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.

Available on the InfraSure platform

See the full revenue + DSCR projection for this project.

10-year revenue projection
First-year DSCR
Financing close risk
Market Context
Approximate
ISO / RTO
ERCOT
Trading Hub
HB_SOUTH
Hub Confidence
LOW

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No insights available for this project.
InfraSure platform

Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.