Tres Rios Ranch Solar (ERCOT-24INR0404) — Project Summary

Queue ID
ERCOT-24INR0404
Capacity
508 MW
Technology
Solar+Battery
Status
active
Location
Upton, TX
Region
ERCOT
Developer
LectricWind LLC
IA Status
Facility Study

Tres Rios Ranch Solar

ERCOT-24INR0404BetaActiveSolarBatteryERCOTLBNL + Live

508 MW hybrid in Upton, TX · In queue since August 2022 · Proposed COD December 2027

BA: ERCOISO/RTO: ERCOTNERC: TRERC: ERCOT

508 MW

Capacity

1

Components

Solar

4y 3m

In Queue

Facility Study

IA Phase

Signed Dec 2025

Asset Intelligence Map

One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.

5 live dimensions
4 decision models

Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.

Structured from the current asset record; empty data branches are omitted.Locked nodes are InfraSure decision models; no simulated values shown.
Interconnection

Queue → IA

3y 4m

IA → COD

2 years

Total Duration

3y 4m

Construction50%
Queue EntryAug 5, 2022

Interconnection request submitted to ISO/RTO

Interconnection Study

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection AgreementDec 30, 2025

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

SS Completed, FIS Started, IA

Project under construction

Typical: 18–30 months

Commercial Operation

Proposed COD: 2027-12-31

Queue history
24INR0404 · 41 monthly ERCOT reports, May 2023 – Sep 2026

Projected COD moved

1 time

Dec 2025 → Dec 2027

Net change

+24 months

first report to latest

Capacity

424 → 508 MW

changed in the reports

Latest stage

IA signed

in ERCOT's latest report

Projected COD in each reportDue now (report date = COD)Milestone first reported
Screening study startedAug 5, 2022
Interconnection agreement signedDec 30, 2025

Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).

Cross-source intelligence

Saved research · Beta
Researched Oct 25, 2026

Experimental assessment saved at the research date. See the queue record for reported project facts.

Research COD
Dec 31, 2027
From queue filing
Developer in saved assessment
LectricWind LLC
From queue filing
Status at research time
Active
Active in ERCOT queue; Facility Study phase, with an IA reportedly signed Dec 2025 per an aggregator. No construction or financing announcement found.
Financing
Not recorded

Milestones in this assessment

IA executedDec 2025Latest in this assessment

Aggregator notes LectricWind signed an interconnection agreement for the 508 MW solar + 290 MW battery Tres Rios Ranch project (Dec 2025). This is inconsistent with the Facility Study status shown elsewhere.

infrasure.ai
Research sources and reasoning (7 recorded sources)

low confidence at research time

  1. interconnection.fyi/project/ercot-24inr0404
  2. infrasure.ai/project/ercot-24inr0404-tres-rios-ranch-solar
  3. infrasure.ai/project/ercot-25inr0451-tres-rios-ranch-bess
  4. ercotqueue.com/project/24INR0404
  5. ercotqueue.com/developer/lectricwind-llc
  6. cleanview.co/power-projects/planned/solar-farms/texas/24INR0404/tres-rios-ranch-solar
  7. interxdata.com/projects/tres-rios-ranch-solar-ercot-gis-report-24inr0404/

Commercial operation date: Only the LBNL proposed COD of 2027-12-31 is available. Aggregators (interconnection.fyi, infrasure.ai, cleanview 'Expected online 2027') repeat the queue date and add no independent developer-backed target.

Developer: All sources name LectricWind LLC, and they appear to derive from the queue filing. No press release identifies a parent or operating company behind it.

Status: LBNL and multiple trackers (ercotqueue.com, interconnection.fyi, infrasure.ai) list the project as active. One aggregator (interxdata) says 'operational', which contradicts the others and the LBNL is_operational=false, so it was disregarded.

About

Saved background

Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source

Figures and claims below reflect the saved summary. See the queue record for reported project facts.

The Tres Rios Ranch Solar project is a proposed 508 MW solar generation facility in Upton County, Texas. Developed by LectricWind LLC, the project is currently active in the ERCOT interconnection queue as entry ERCOT-24INR0404, with a queue entry date of August 5, 2022. The proposed commercial operation date is December 31, 2027.

The project's interconnection status is currently in the Facility Study phase. The point of interconnection is the 76008 Twelvemile 345kV location. The Tres Rios Ranch Solar project has appeared in recent news coverage.

Summary provenance

Summary generated Apr 10, 2026 (UTC).

Source dates used by this summary were not recorded.

Dates in the current asset record

These may postdate the saved summary; they do not establish which inputs it used.

  • ERCOT queue source as of: Oct 1, 2026.
  • Queue history observations through: Sep 2026.
Development Risk

Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.

Available on the InfraSure platform

See the full development-risk decomposition for this project.

P(COD by stated date)
Withdrawal probability vs cohort
IA cluster risk
Project Details

State

TX

County

Upton

Grid Region

ERCOT (Texas)

Market

ISO/RTO Member

Developer

LectricWind LLC

Utility

—

Entity

ERCOT

Service Type

—

Point of Interconnection

76008 Twelvemile 345kV

Data Source

LBNL + Live

Risk Analytics

Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.

Available on the InfraSure platform

See the full risk decomposition + scenarios for this project.

Climate hazards (8+)
Generation variability (P10/P50/P90)
Offtake + transmission counterparty
Generation Forecast

Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.

Available on the InfraSure platform

See the full forecast + scenario decomposition for this project.

P50 conditioned on COD
Capacity factor vs cohort
Weather + policy scenarios
Financial Forecast

Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.

Available on the InfraSure platform

See the full revenue + DSCR projection for this project.

Revenue conditioned on COD
Financing close risk
Cohort DSCR comparison
Market Context
Approximate
ISO / RTO
ERCOT
Trading Hub
HB_WEST
Hub Confidence
LOW

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No insights available for this project.
InfraSure platform

Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.