Tres Rios Ranch BESS
290 MW generation in Upton, TX · In queue since May 2023 · Proposed COD December 2027
290 MW
Capacity
1
Components
Battery
3y 6m
In Queue
Facility Study
IA Phase
Signed Dec 2025
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Queue → IA
2y 7m
IA → COD
2 years
Total Duration
2y 7m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
SS Completed, FIS Started, IA
Project under construction
Typical: 18–30 months
Proposed COD: 2027-12-31
Projected COD moved
1 time
Dec 2025 → Dec 2027
Net change
+24 months
first report to latest
Capacity
242 → 290 MW
changed in the reports
Latest stage
IA signed
in ERCOT's latest report
Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).
Cross-source intelligence
Experimental assessment saved at the research date. Predates the Oct 1, 2026 queue source. See the queue record for reported project facts.
Milestones in this assessment
LectricWind signed interconnection agreement for 508 MW solar + 290 MW battery Tres Rios Ranch project
cleanview.coResearch sources and reasoning (3 recorded sources)
medium confidence at research time
- cleanview.co/news/hybrid/lectricwind-signs-interconnection-agreement-for-508-mw-tres-rios-ranch-solar-20260128
- ercotqueue.com/project/25INR0451
- ercotqueue.com/developer/lectricwind-llc
Commercial operation date: LBNL queue snapshot shows proposed COD of 2027-12-31. No independent news sources provide alternative COD targets; Cleanview aggregator mirrors LBNL date. January 2026 press release confirms IA signing but does not specify revised COD.
Developer: LBNL filing entity 'LectricWind LLC' appears to be the operating company itself, not a project-specific shell LLC. All sources (Cleanview, ercotqueue.com, ERCOT filings) consistently reference LectricWind LLC as developer with no parent company identified.
Status: LBNL shows 'active' status at Facility Study stage. January 28, 2026 Cleanview article confirms LectricWind signed interconnection agreement for the project, advancing from queue position to formal IA execution.
About
Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
The Tres Rios Ranch BESS is a proposed 290 MW battery storage project in Upton County, Texas. Developed by LectricWind LLC, the project is currently active in the ERCOT interconnection queue as entry ERCOT-25INR0451, with a queue entry date of May 26, 2023. Its proposed commercial operation date is December 31, 2027, and its interconnection agreement status is currently in the Facility Study phase.
The project consists of 290 MW of battery storage capacity. The point of interconnection is the 76008 Twelvemile 345kV location. The Tres Rios Ranch BESS project has appeared in recent news coverage.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- ERCOT queue source as of: Oct 1, 2026.
- Queue history observations through: Sep 2026.
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Upton
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
LectricWind LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
76008 Twelvemile 345kV
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_WEST
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Battery storage projects in ERCOT
Data tables and metrics from the InfraSure database.
Tres Rios Ranch BESS
Data-driven briefing on Tres Rios Ranch BESS — fleet, generation, financial, and news signals.
Battery storage pipeline in ERCOT
Data tables and metrics from the InfraSure database.
Rio
Data-driven briefing on Rio — fleet, generation, financial, and news signals.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.