Pradera Solar
118 MW hybrid in Webb, TX · In queue since July 2021 · Proposed COD March 2027
118 MW
Capacity
1
Components
Solar
5y 4m
In Queue
Facility Study
IA Phase
COD target: 2027
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Total Duration
5y 8m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-03-31
Projected COD moved
1 time
Oct 2024 → Mar 2027
Net change
+29 months
first report to latest
Capacity
118 MW
unchanged in the reports
Latest stage
Cancelled
last listed Mar 2026
Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).
Cross-source intelligence
Experimental assessment saved at the research date. See the queue record for reported project facts.
Milestones in this assessment
Webb County tax abatement agreement executed for $30M renewable energy project
webbcountytx.govResearch sources and reasoning (4 recorded sources)
medium confidence at research time
- interconnection.fyi/project/ercot-24inr0056
- webbcountytx.gov/TaxAbatementAgreements/9-26-22%20Item%2023%20-%20Pradera%20Tax%20Abatement%20Agreement.pdf
- subsidytracker.goodjobsfirst.org/?statesum=TX&detail=c&order=parent_name&sort=asc&page=80
- comptroller.texas.gov/economy/docs/active-list.xlsx
Commercial operation date: Only LBNL queue data provides a COD target of 2027-03-31. No press releases, news articles, or developer announcements found to confirm or update this date.
Developer: All sources consistently identify 'Pradera Solar, LLC' as a Delaware LLC project entity. No parent company or operating entity identified in any search results; appears to be a standalone project SPV.
Status: Interconnection.fyi (Result 3) explicitly states the project is 'currently withdrawn in the ERCOT' queue, contradicting LBNL's 'active' status which may be stale.
About
Generated Apr 10, 2026
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
Pradera Solar is a proposed 118 MW solar generation project located in Webb County, Texas. The project, developed by Pradera Solar, LLC, is in the ERCOT interconnection queue as entry ERCOT-24INR0056, with a queue entry date of July 8, 2021. The proposed commercial operation date is March 31, 2027.
The project's interconnection status is currently in the Facility Study phase. The point of interconnection is the tap 345 kV Lobo (80219) - Fowlerton (5709).
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- LBNL queue source as of: Dec 31, 2025.
- Queue history observations through: Mar 2026.
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Webb
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Pradera Solar, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
tap 345 kV Lobo (80219) - Fowlerton (5709)
Data Source
LBNL
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_SOUTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.