Smokey Willie Solar SLF (ERCOT-23INR0439) — Project Summary

Queue ID
ERCOT-23INR0439
Capacity
201.04 MW
Technology
Solar+Battery
Status
active
Location
Anderson, TX
Region
ERCOT
Developer
Neches Solar, LLC
IA Status
Facility Study

Smokey Willie Solar SLF

ERCOT-23INR0439BetaActiveSolarBatteryERCOTLBNL + Live

201.04 MW hybrid in Anderson, TX · In queue since January 2022 · Proposed COD September 2028

BA: ERCOISO/RTO: ERCOTNERC: TRERC: ERCOT

201.04 MW

Capacity

1

Components

Solar

4y 10m

In Queue

Facility Study

IA Phase

COD target: 2028

Asset Intelligence Map

One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.

5 live dimensions
4 decision models

Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.

Structured from the current asset record; empty data branches are omitted.Locked nodes are InfraSure decision models; no simulated values shown.
Interconnection

Total Duration

6y 8m

Facilities Study50%
Queue EntryJan 6, 2022

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

SS Completed, FIS Started, No IA

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2028-09-30

Queue history
23INR0439 · 57 monthly ERCOT reports, Jan 2022 – Sep 2026

Projected COD moved

6 times

Dec 2023 → Sep 2028

Net change

+57 months

first report to latest

Capacity

201 → 201 MW

changed in the reports

Latest stage

Facilities study done

in ERCOT's latest report

Projected COD in each reportDue now (report date = COD)Milestone first reported
Screening study startedJan 6, 2022
Facilities study approvedSep 22, 2023

Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).

Cross-source intelligence

Saved research · Beta
Researched Jun 1, 2026

Experimental assessment saved at the research date. Predates the Oct 1, 2026 queue source. Research and queue COD differ; this comparison does not confirm either date. See the queue record for reported project facts.

Research COD
Mar 13, 2026
Differs from queue: Sep 30, 2028
Developer in saved assessment
Neches Solar, LLC
From queue filing
Status at research time
Active
Active — Facility Study stage in ERCOT interconnection queue, targeting 2026 COD
Financing
Not recorded

Milestones in this assessment

COD targetMar 13, 2026Latest in this assessment

In Service Date reported as March 13, 2026

futuregrid.io
Research sources and reasoning (4 recorded sources)

medium confidence at research time

  1. eta-publications.lbl.gov/sites/default/files/2024-09/hybrid_plant_tracking_2024_data_workbook.xlsx
  2. renewablesinfo.org/browse/projects/texas
  3. futuregrid.io/interconnections/smokey-willie-solar-slf/
  4. infrasure.ai/project/ercot-23inr0439-smokey-willie-solar-slf

Commercial operation date: FutureGrid reports In Service Date of 13/03/2026 (March 13, 2026), which is 2.5 years earlier than LBNL's proposed COD of 2028-09-30. This represents a significant disagreement indicating LBNL data is stale.

Developer: All sources consistently identify Neches Solar, LLC as the developer with no evidence of a parent company or shell LLC structure. No ownership changes or acquisitions found.

Status: LBNL reports Active status at Facility Study stage. No evidence of construction start, withdrawal, or status change in available sources.

About

Saved background

Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source

Figures and claims below reflect the saved summary. See the queue record for reported project facts.

The Smokey Willie Solar SLF project is a proposed 200.92 MW solar generation facility in Anderson County, Texas. The project, being developed by Neches Solar, LLC, is currently active in the ERCOT interconnection queue as entry ERCOT-23INR0439, with a queue entry date of January 6, 2022. The proposed commercial operation date is September 30, 2028.

The project's interconnection status is currently in the Facility Study phase. The point of interconnection is Tap 138kV 3325 Blackburn Switch _x0013_ 3272 Palestine. The project consists of 200.92 MW of solar photovoltaic generation.

Summary provenance

Summary generated Apr 10, 2026 (UTC).

Source dates used by this summary were not recorded.

Dates in the current asset record

These may postdate the saved summary; they do not establish which inputs it used.

  • ERCOT queue source as of: Oct 1, 2026.
  • Queue history observations through: Sep 2026.
Development Risk

Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.

Available on the InfraSure platform

See the full development-risk decomposition for this project.

P(COD by stated date)
Withdrawal probability vs cohort
IA cluster risk
Project Details

State

TX

County

Anderson

Grid Region

ERCOT (Texas)

Market

ISO/RTO Member

Developer

Neches Solar, LLC

Utility

—

Entity

ERCOT

Service Type

—

Point of Interconnection

Tap 138kV 3325 Blackburn Switch – 3272 Palestine

Data Source

LBNL + Live

Risk Analytics

Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.

Available on the InfraSure platform

See the full risk decomposition + scenarios for this project.

Climate hazards (8+)
Generation variability (P10/P50/P90)
Offtake + transmission counterparty
Generation Forecast

Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.

Available on the InfraSure platform

See the full forecast + scenario decomposition for this project.

P50 conditioned on COD
Capacity factor vs cohort
Weather + policy scenarios
Financial Forecast

Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.

Available on the InfraSure platform

See the full revenue + DSCR projection for this project.

Revenue conditioned on COD
Financing close risk
Cohort DSCR comparison
Market Context
Approximate
ISO / RTO
ERCOT
Trading Hub
HB_NORTH
Hub Confidence
LOW

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No insights available for this project.