CH Solterra LLC (ERCOT-23INR0229) — Project Summary

Queue ID
ERCOT-23INR0229
Capacity
143 MW
Technology
Solar
Status
active
Location
Hopkins, TX
Region
ERCOT
Developer
CH Solterra LLC
IA Status
Facility Study

CH Solterra LLC

ERCOT-23INR0229BetaActiveSolarERCOTLBNL + Live

143 MW generation in Hopkins, TX · In queue since March 2021 · Proposed COD May 2027

BA: ERCOISO/RTO: ERCOTNERC: TRERC: ERCOT

143 MW

Capacity

1

Components

Solar

5y 8m

In Queue

Facility Study

IA Phase

COD target: 2027

Asset Intelligence Map

One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.

5 live dimensions
4 decision models

Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.

Structured from the current asset record; empty data branches are omitted.Locked nodes are InfraSure decision models; no simulated values shown.
Interconnection

Total Duration

6y 2m

Facilities Study50%
Queue EntryMar 19, 2021

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

SS Completed, FIS Started, No IA

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2027-05-31

Queue history
23INR0229 · 65 monthly ERCOT reports, Mar 2021 – Sep 2026

Projected COD moved

8 times

May 2023 → May 2027

Net change

+48 months

first report to latest

Capacity

143 MW

unchanged in the reports

Latest stage

Facilities study done

in ERCOT's latest report

Projected COD in each reportDue now (report date = COD)Milestone first reported
Screening study startedMar 19, 2021
Facilities study approvedMar 23, 2022
On ERCOT's inactive listMar 2022 – Apr 2022

Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).

Cross-source intelligence

Saved research · Beta
Researched Jun 1, 2026

Experimental assessment saved at the research date. Predates the Oct 1, 2026 queue source. Research and queue COD differ; this comparison does not confirm either date. See the queue record for reported project facts.

Research COD
Dec 31, 2026
Differs from queue: May 31, 2027From queue filing
Developer in saved assessment
CH Solterra LLC
From queue filing
Status at research time
Active
Active — Facility Study phase; Standard Generation Interconnection Agreement filed with Oncor October 2024
Financing
Not recorded
Ownership history
  1. 2021-11·BT Solterra Solar, LLC→CH Solterra LLCcomptroller.texas.gov

Milestones in this assessment

Permit approvedAug 2022

Chapter 313 tax abatement agreement and findings approved by Saltillo ISD

comptroller.texas.gov
IA executedSep 14, 2024

Standard Generation Interconnection Agreement executed between Oncor and CH Solterra, filed with PUC October 2024

interchange.puc.texas.gov
Permit approvedMar 10, 2026Latest in this assessment

Hopkins County Commissioners approved expansion of solar projects including CH Solterra

ksstradio.com
Research sources and reasoning (4 recorded sources)

medium confidence at research time

  1. comptroller.texas.gov/economy/development/prop-tax/ch313/agreement-docs-details.php?id=1662
  2. interchange.puc.texas.gov/Documents/35077_1952_1433941.PDF
  3. ksstradio.com/2026/03/hopkins-county-commissioners-approve-new-solar-projects/
  4. interconnectionfyi.substack.com/p/interconnection-weekly-project-updates-7d3

Commercial operation date: LBNL queue shows December 2026 COD. Cleanview aggregator sites echo this date, but no independent developer press release or financing announcement confirms it. January 2025 Interconnection FYI notes a proposed completion change to August 2027 for an unspecified aspect, creating minor uncertainty.

Developer: Texas Comptroller records show the entity was formerly 'BT Solterra Solar, LLC' (f/k/a filing from Nov 2021). No parent company or operating entity identified in search results; CH Solterra LLC appears to be the actual developer, not a shell. No acquisition or ownership transfer found beyond the name change from BT Solterra.

Status: LBNL shows 'active' status in Facility Study phase. October 2024 PUC filing confirms Standard Generation Interconnection Agreement between Oncor and CH Solterra, indicating project remains active and progressing through interconnection process.

About

Saved background

Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source

Figures and claims below reflect the saved summary. See the queue record for reported project facts.

CH Solterra LLC is a proposed solar generation project located in Hopkins County, Texas, within the ERCOT region. The project, developed by CH Solterra LLC, has a total capacity of 143 MW. It entered the ERCOT interconnection queue as project ERCOT-23INR0229 on March 19, 2021, and has a proposed commercial operation date of December 31, 2026. The project's interconnection status is currently in the Facility Study phase.

The proposed project consists of 143 MW of solar generation capacity. It is currently listed as active within the ERCOT interconnection queue. Recent news coverage has discussed the project's progress and potential impact on the region's energy landscape.

Summary provenance

Summary generated Apr 10, 2026 (UTC).

Source dates used by this summary were not recorded.

Dates in the current asset record

These may postdate the saved summary; they do not establish which inputs it used.

  • ERCOT queue source as of: Oct 1, 2026.
  • Queue history observations through: Sep 2026.
Development Risk

Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.

Available on the InfraSure platform

See the full development-risk decomposition for this project.

P(COD by stated date)
Withdrawal probability vs cohort
IA cluster risk
Project Details

State

TX

County

Hopkins

Grid Region

ERCOT (Texas)

Market

ISO/RTO Member

Developer

CH Solterra LLC

Utility

—

Entity

ERCOT

Service Type

—

Point of Interconnection

Tap 138kV 11796 White Oak POI - 11797 Brinker POI

Data Source

LBNL + Live

Risk Analytics

Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.

Available on the InfraSure platform

See the full risk decomposition + scenarios for this project.

Climate hazards (8+)
Generation variability (P10/P50/P90)
Offtake + transmission counterparty
Generation Forecast

Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.

Available on the InfraSure platform

See the full forecast + scenario decomposition for this project.

P50 conditioned on COD
Capacity factor vs cohort
Weather + policy scenarios
Financial Forecast

Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.

Available on the InfraSure platform

See the full revenue + DSCR projection for this project.

Revenue conditioned on COD
Financing close risk
Cohort DSCR comparison
Market Context
Approximate
ISO / RTO
ERCOT
Trading Hub
HB_HOUSTON
Hub Confidence
MEDIUM
POI Substation
White Oak Substation

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No insights available for this project.