GREASEWOOD ENERGY STORAGE
513.2 MW storage in Kern, CA · In queue since April 2021 · Proposed COD June 2031
513.2 MW
Capacity
1
Components
Battery
5y 7m
In Queue
IA Executed
IA Phase
Signed Oct 2025
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Queue → IA
4y 6m
IA → COD
5y 8m
Total Duration
4y 6m
Study Phase
C14
Interconnection request submitted to ISO/RTO
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Active sheet; IA Executed; C14
Project under construction
Typical: 6–18 months
Proposed COD: 2031-06-01
Cross-source intelligence
Experimental assessment saved at the research date. See the queue record for reported project facts.
Milestones in this assessment
Interconnection agreement executed for the 513.2 MW Greasewood battery project (Whirlwind 500 kV, SCE).
infrasure.aiResearch sources and reasoning (5 recorded sources)
low confidence at research time
- infrasure.ai/project/caiso-2089-greasewood-energy-storage
- interconnection.fyi/project/caiso-2089
- cleanview.co/power-projects/planned/battery-storage-projects/california/2089_storage/greasewood-energy-storage
- interxdata.com/projects/greasewood-energy-storage-caiso-public-queue-2089/
- interxdata.com/projects/greasewood-energy-storage-ii-caiso-54895/
Commercial operation date: Only the LBNL proposed COD (2031-06-01) is supported; Cleanview also lists 'Expected online 2031' but appears to be derived from the queue data. Infrasure's text cites an inconsistent 2033-02-26 date alongside 2031-06-01, and no developer press release or news item gives an independent target.
Developer: LBNL developer field is null and no search result names a developer or parent for Greasewood Energy Storage. The Intersect Power result concerns a Texas solar project and is unrelated.
Status: LBNL shows active status with IA executed on 2025-10-06, and Infrasure confirms the IA signing in Oct 2025. No news indicates construction start, withdrawal, or suspension. The withdrawn 'Greasewood Energy Storage II' (54895) is a separate queue entry.
About
Generated Apr 10, 2026 · Predates Oct 24, 2026 queue source
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
The proposed GREASEWOOD ENERGY STORAGE project is a 513.2 MW battery storage development in Kern County, California. Interconnection is requested through the CAISO queue (queue ID CAISO-2089) with Southern California Edison (SCE) as the utility. The project entered the queue on April 15, 2021, and has a proposed commercial operation date of February 26, 2033. The interconnection status is currently in the System Impact Study phase.
The project is located at the Whirlwind Substation 500 kV Point of Interconnection. Recent news coverage has discussed the project.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- CAISO queue source as of: Oct 24, 2026.
Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
CA
County
Kern
Grid Region
CAISO (California)
Market
ISO/RTO Member
Developer
—
Utility
SCE
Entity
CAISO
Service Type
NRIS
Point of Interconnection
Whirlwind Substation 500 kV
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- CAISO
- Trading Hub
- TH_SP15_GEN-APND
- Hub Confidence
- MEDIUM
- Nearest Node (Estimated)
- ASTORIA2_7_N001
- POI Substation
- Whirlwind Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Battery Storage queue pipeline by status
Data tables and metrics from the InfraSure database.
Battery storage queue pipeline
Summary analysis with parallel narrative sections and visualizations.
Battery Storage queue pipeline overview
Summary analysis with parallel narrative sections and visualizations.
GREASEWOOD ENERGY STORAGE
Data-driven briefing on GREASEWOOD ENERGY STORAGE — fleet, generation, financial, and news signals.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.