EL REY POWER BANK
124.3 MW storage in Monterey, CA · In queue since April 2021 · Proposed COD January 2029
124.3 MW
Capacity
1
Components
Battery
5y 3m
In Queue
System Impact Study
IA Phase
COD target: 2029
Total Duration
7y 9m
Study Phase
C14
Interconnection request submitted to ISO/RTO
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2029-01-02
The El Rey Power Bank is a proposed 124.3 MW battery storage project in Monterey County, California. The project is located within the CAISO region and is being developed for Pacific Gas & Electric (PGAE). It entered the CAISO interconnection queue as queue ID CAISO-1928 on April 15, 2021. The proposed commercial operation date is January 2, 2029, and its interconnection status is currently in the System Impact Study phase.
The El Rey Power Bank development has been the subject of recent news coverage, with five articles appearing in the press. These articles cover topics such as potential hazards, deals, industry trends, and project development.
Generated from interconnection queue and public data sources
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
CA
County
Monterey
Grid Region
CAISO (California)
Market
ISO/RTO Member
Developer
—
Utility
PGAE
Entity
CAISO
Service Type
ERIS
Point of Interconnection
Coburn-Basic Energy 60 kV Line
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- CAISO
- Trading Hub
- TH_ZP26_GEN-APND
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about EL REY POWER BANKForward forecasts, scenario decomposition, and risk-decision tooling for this queue project.