EL REY POWER BANK
124.3 MW storage in Monterey, CA · In queue since April 2021 · Proposed COD January 2029
124.3 MW
Capacity
1
Components
Battery
5y 7m
In Queue
System Impact Study
IA Phase
COD target: 2029
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Total Duration
7y 9m
Study Phase
C14
Interconnection request submitted to ISO/RTO
Active sheet; C14
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2029-01-02
From dated articles. These observations may describe earlier stages or other project phases; see the queue record above for reported filing status.
Cross-source intelligence
Experimental assessment saved at the research date. Predates the Oct 24, 2026 queue source. See the queue record for reported project facts.
Milestones in this assessment
Entered CAISO queue as Q1928, System Impact Study phase
caiso.comResearch sources and reasoning (4 recorded sources)
low confidence at research time
- cleanview.co/power-projects/planned/battery-storage-projects/california/1928_storage/el-rey-power-bank
- infrasure.ai/project/caiso-1928-el-rey-power-bank
- caiso.com/documents/publicqueuereport.xlsx
- docs.cpuc.ca.gov/PublishedDocs/Efile/G000/M534/K048/534048570.PDF
Commercial operation date: Only LBNL queue data provides a COD target of 2029-01-02. No news articles, press releases, or developer announcements found to validate or update this date.
Developer: LBNL snapshot shows null developer. No press releases, corporate announcements, or ownership records found in search results. Project appears in queue tracking databases only.
Status: LBNL reports 'active' status at System Impact Study phase. No contradictory evidence or advancement signals found in public sources.
About
Generated Apr 10, 2026 · Predates Oct 24, 2026 queue source
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
The El Rey Power Bank is a proposed 124.3 MW battery storage project in Monterey County, California. The project is located within the CAISO region and is being developed for Pacific Gas & Electric (PGAE). It entered the CAISO interconnection queue as queue ID CAISO-1928 on April 15, 2021. The proposed commercial operation date is January 2, 2029, and its interconnection status is currently in the System Impact Study phase.
The El Rey Power Bank development has been the subject of recent news coverage, with five articles appearing in the press. These articles cover topics such as potential hazards, deals, industry trends, and project development.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- CAISO queue source as of: Oct 24, 2026.
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
CA
County
Monterey
Grid Region
CAISO (California)
Market
ISO/RTO Member
Developer
—
Utility
PGAE
Entity
CAISO
Service Type
ERIS
Point of Interconnection
Coburn-Basic Energy 60 kV Line
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- CAISO
- Trading Hub
- TH_ZP26_GEN-APND
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Last updated 2026-03-14
View all articlesForward forecasts, scenario decomposition, and risk-decision tooling for this queue project.