PSE-153
188 MW generation in Skagit, WA · In queue since April 2024 · Proposed COD December 2028
188 MW
Capacity
1
Components
Gas
2y 3m
In Queue
Cluster Study
IA Phase
COD target: 2028
Total Duration
4y 8m
Study Phase
1
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-12-31
PSE-153 is a proposed 188 MW gas-fired generation project located in Skagit County, Washington. The project, under development by Puget Sound Energy (PSE), is interconnected to the Fredonia 230 kV Substation. It entered the Puget Sound Energy interconnection queue on April 17, 2024, with a proposed commercial operation date of December 31, 2028. Its interconnection status is currently in the Cluster Study phase.
The project consists of 188 MW of gas-fired generation capacity. It is listed as an active project in the interconnection queue. The project has appeared in recent news coverage regarding Puget Sound Energy's resource planning.
Generated from interconnection queue and public data sources
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
WA
County
Skagit
Grid Region
Mountain West
Market
—
Developer
—
Utility
Puget Sound Energy
Entity
PSE
Service Type
NRIS
Point of Interconnection
Fredonia 230 kV Substation
Data Source
LBNL
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- MID-C
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Project PSE-153Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.