PNM-IA-PNM-2021-10
300 MW hybrid in Bernalillo, NM · In queue since July 2021 · Proposed COD June 2025
300 MW
Capacity
1
Components
Solar
5y 4m
In Queue
IA Executed
IA Phase
COD target: 2025
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Total Duration
3y 11m
Schedule
18 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 18–30 months
Proposed COD: 2025-06-01
Cross-source intelligence
Experimental assessment saved at the research date. See the queue record for reported project facts.
Research sources and reasoning (0 recorded sources)
low confidence at research time
No source list recorded with this assessment.
Commercial operation date: Only the LBNL snapshot provides a COD (proposed_cod 2025-06-01). No news or search findings were available to confirm or revise it, so it may be stale.
Developer: LBNL lists 'NextEra Energy' as developer. No press releases or search results were available to identify a project LLC, parent, or ownership change.
Status: LBNL ia_status is 'IA Executed' and status is 'active', with is_operational false. No other sources were available to refine this.
About
Generated Apr 10, 2026
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
PNM-IA-PNM-2021-10 is a proposed 300 MW hybrid solar and battery project located in Bernalillo County, New Mexico. The development project, which appeared in the Public Service Company of New Mexico (PNM) interconnection queue on July 9, 2021, consists of 300 MW of solar capacity. NextEra Energy is listed as the developer.
The project is in the PNM queue and has an interconnection agreement (IA) executed. The proposed commercial operation date is June 1, 2025, and the point of interconnection is the Pajarito-345 kV Substation.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- LBNL queue source as of: Dec 31, 2025.
Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
NM
County
Bernalillo
Grid Region
Mountain West
Market
—
Developer
NextEra Energy
Utility
Public Service Company of New Mexico
Entity
PNM
Service Type
ERIS
Point of Interconnection
Pajarito- 345 kV Substation
Data Source
LBNL
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- FOURCORNERS
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
A specific company (e.g., NextEra Energy, Duke Energy)
Data-driven briefing on NextEra Energy — fleet, generation, financial, and news signals.
NextEra Energy
Data-driven briefing on NextEra Energy — fleet, generation, financial, and news signals.
NextEra entity test
Data-driven briefing on NextEra Energy — fleet, generation, financial, and news signals.
NextEra-Blackwell Wind, LLC
Data-driven briefing on NextEra Energy — fleet, generation, financial, and news signals.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.