PNM-IA-PNM-2021-09
150 MW hybrid in Bernalillo, NM · In queue since July 2021 · Proposed COD June 2025
150 MW
Capacity
1
Components
Solar
5y 4m
In Queue
IA Executed
IA Phase
COD target: 2025
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Total Duration
3y 11m
Schedule
18 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 18–30 months
Proposed COD: 2025-06-01
Cross-source intelligence
Experimental assessment saved at the research date. See the queue record for reported project facts.
Milestones in this assessment
Interconnection Agreement executed with PNM per LBNL queue status
Research sources and reasoning (0 recorded sources)
low confidence at research time
No source list recorded with this assessment.
Commercial operation date: Only LBNL queue data available showing June 2025 COD. No independent news or research sources to validate or contradict this date.
Developer: LBNL lists 'NextEra Energy' as developer, which appears to be the parent operating company rather than a project LLC. No additional sources to confirm or identify a separate legal entity.
Status: LBNL shows IA Executed status with active queue position. No news coverage to confirm current construction or development phase.
About
Generated Apr 10, 2026
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
The proposed project PNM-IA-PNM-2021-09 is a 150 MW solar and battery hybrid project located in Bernalillo County, New Mexico. The developer is NextEra Energy, and the project is interconnected with Public Service Company of New Mexico (PNM). The solar component has a capacity of 150 MW.
This development project is in the PNM interconnection queue, with an original queue entry date of July 9, 2021, and a proposed commercial operation date of June 1, 2025. The interconnection agreement (IA) has been executed. The point of interconnection (POI) is the Los Morros - West Mesa 115 kV Line.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- LBNL queue source as of: Dec 31, 2025.
Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
NM
County
Bernalillo
Grid Region
Mountain West
Market
—
Developer
NextEra Energy
Utility
Public Service Company of New Mexico
Entity
PNM
Service Type
ERIS
Point of Interconnection
Los Morros - West Mesa 115 kV Line
Data Source
LBNL
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- FOURCORNERS
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
A specific company (e.g., NextEra Energy, Duke Energy)
Data-driven briefing on NextEra Energy — fleet, generation, financial, and news signals.
NextEra Energy
Data-driven briefing on NextEra Energy — fleet, generation, financial, and news signals.
NextEra entity test
Data-driven briefing on NextEra Energy — fleet, generation, financial, and news signals.
NextEra-Blackwell Wind, LLC
Data-driven briefing on NextEra Energy — fleet, generation, financial, and news signals.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.