Nicholas Solar
100 MW generation in Nicholas, WV · In queue since March 2020 · Proposed COD February 2029
100 MW
Capacity
1
Components
Solar
6y 8m
In Queue
IA Executed
IA Phase
COD target: 2029
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Total Duration
8y 11m
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Engineering and Procurement
Project under construction
Typical: 12–24 months
Proposed COD: 2029-02-28
Cross-source intelligence
Experimental assessment saved at the research date. Predates the Oct 25, 2026 queue source. See the queue record for reported project facts.
Milestones in this assessment
Interconnection Agreement executed per LBNL queue status (exact date unavailable)
West Virginia Public Service Commission approved siting for Nicholas Solar project
wvmetronews.comResearch sources and reasoning (1 recorded sources)
medium confidence at research time
Commercial operation date: Only LBNL queue data provides a COD target of Feb 2029. No news sources mention construction timeline or updated COD targets.
Developer: News extraction identifies 'Deep Lake Energy Center' as the applicant in PSC filings from Aug 2024. LBNL queue snapshot has null developer field, so no shell-LLC vs parent comparison possible.
Status: LBNL shows 'Active' with IA Executed status. WV PSC approval granted Aug 2024 confirms project advancing through permitting milestones.
About
Generated Apr 10, 2026 · Predates Oct 25, 2026 queue source
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
The Nicholas Solar project is a proposed 100 MW solar generation facility in Nicholas County, West Virginia. The project is located within the PJM Interconnection region and is being developed by an unknown entity. It consists of 100 MW of solar photovoltaic generation.
The project entered the PJM interconnection queue as queue ID PJM-AF2-311 on March 30, 2020, with a proposed commercial operation date of February 28, 2029. The interconnection agreement (IA) has been executed. The point of interconnection (POI) is the Gilboa-Jones Branch 138 kV line. The Nicholas Solar project has been mentioned in recent news coverage.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- PJM queue source as of: Oct 25, 2026.
Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
WV
County
Nicholas
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
APS
Entity
PJM
Service Type
NRIS
Point of Interconnection
Gilboa-Jones Branch 138 kV
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- PJM
- Trading Hub
- AEP-DAYTON HUB
- Hub Confidence
- HIGH
- POI Substation
- Branch
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Last updated 2026-03-26