Briefing on Nicholas Solar

Entity Briefing
Generated Oct 17, 2026·Dataset freshness not reported
100 MW
Proposed capacity
active
Current status
Solar
Technology
PJM
Market / region
2029-02-28
Proposed COD
IA Executed
Queue phase
Briefing/projectactive

Nicholas Solar is a 100 MW Solar project in West Virginia, currently active.

The reported queue phase is IA Executed. Proposed COD is 2029-02-28.

Queue ID
PJM-AF2-311
Location
Nicholas, West Virginia
Technology
Solar
Market / region
PJM
Point of interconnection
Gilboa-Jones Branch 138 kV

What stands out

1

Nicholas Solar is a 100 MW Solar project in West Virginia with status active.

2

The reported queue phase is IA Executed; proposed COD is 2029-02-28.

3

Latest linked story: “PSC approves solar project on Nicholas-Clay county line” (WV MetroNews, 2024-08-06).

Market and operating context

Queue date
2020-03-30
Proposed COD
2029-02-28
IA status
IA Executed
Study phase
IA Executed
Service type
NRIS

Why it matters

Queue phase, proposed timing, developer identity, and linked events determine how much of the stated pipeline should be treated as actionable development capacity. The project page and deeper report preserve those fields for further diligence.

Nicholas Solar — verified asset snapshot

FieldValue
Queue IDPJM-AF2-311
LocationNicholas, West Virginia
TechnologySolar
Market / regionPJM
Point of interconnectionGilboa-Jones Branch 138 kV
Queue date2020-03-30
Proposed COD2029-02-28
IA statusIA Executed