CVOW 3, OSS 3 – T3G15
820 MW generation in City Of Chesapeake, VA · In queue since September 2019 · Proposed COD December 2032
820 MW
Capacity
1
Components
Offshore Wind
7y 2m
In Queue
IA Pending
IA Phase
COD target: 2032
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Total Duration
13y 3m
Study Phase
TC1
Interconnection request submitted to ISO/RTO
UC-ISP; FINAL AGREEMENT; TC1
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2032-12-31
Cross-source intelligence
Experimental assessment saved at the research date. See the queue record for reported project facts.
Research sources and reasoning (6 recorded sources)
low confidence at research time
- app.nrgmap.com/queues/lbnl-pjm-af1-125
- infrasure.ai/project/pjm-af1-125-cvow-3-oss-3-t3g15
- cleanview.co/power-projects/planned/wind-farms/virginia/AF1-125%20-%20moved%20to%20TC1/cvow-3-oss-3--t3g15
- pilotonline.com/2026/09/06/dominions-offshore-turbines-multiply-despite-trumps-war-on-wind/
- coastalvawind.com/resources/docs/20260901_september_mariner_update.pdf
- courthousenews.com/wp-content/uploads/2026/01/virginia-electric-and-power-company-v-united-states-department-of-the-interior.pdf
Commercial operation date: Only the LBNL-derived data (NRG Map: 'Proposed online 2032-12-31', Cleanview: 'Expected online 2032') gives a date for this queue position. Infrasure lists 2024-12-31, but that conflicts with the LBNL value and looks like an aggregator error. No developer or press source gives a COD for this specific position. The 2.6 GW CVOW construction coverage does not state one.
Developer: The LBNL filer is the Dominion utility itself, and the federal court filings name 'Virginia Electric and Power Company, d/b/a Dominion Energy Virginia' with OSW Project LLC as plaintiffs. That is consistent with the LBNL filer, so there is no shell-LLC discrepancy for this queue entry.
Status: LBNL shows 'active' as of 31 Dec 2025 with IA Pending and no IA date. Recent coverage (Sep 2026) says CVOW construction is continuing despite federal opposition. Nothing indicates withdrawal or suspension of this queue position.
About
Generated Apr 10, 2026 · Predates Oct 23, 2026 queue source
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
PJM-AF1-125 is a proposed 820 MW offshore wind generation project located in the City Of Chesapeake, Virginia. The project, developed by Dominion, entered the PJM interconnection queue on September 17, 2019, with a proposed commercial operation date of December 31, 2024. Its interconnection status is currently in the System Impact Study phase.
The proposed project consists of 820 MW of offshore wind capacity. The point of interconnection is at Oceana 230 kV. The project is currently listed as active in the PJM queue and has appeared in recent news coverage regarding offshore wind development in the region.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- PJM_CYCLE queue source as of: Oct 23, 2026.
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
VA
County
City Of Chesapeake
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
Virginia Electric and Power Company (d/b/a Dominion Energy Virginia)
Utility
Dominion
Entity
PJM
Service Type
NRIS
Point of Interconnection
Harper 230 kV
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- PJM
- Trading Hub
- DOMINION HUB
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- HARPER 138 KV MOBILE
- POI Substation
- Harper Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Geothermal queue pipeline overview
Summary analysis with parallel narrative sections and visualizations.
Max 4 Wind
Data tables and metrics from the InfraSure database.
Bedford Solar (Dominion)
Data-driven briefing on Dominion Energy — fleet, generation, financial, and news signals.
FPL Energy Oliver Wind II LLC
Cross-dimensional entity briefing with KPIs, news intelligence, and fleet analysis.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.