Yellow Wood Solar Energy Center
300 MW generation in Clinton, OH · In queue since March 2019 · Proposed COD December 2027
300 MW
Capacity
1
Components
Solar
7y 8m
In Queue
IA Executed
IA Phase
COD target: 2027
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Total Duration
8y 9m
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Under Construction
Project under construction
Typical: 12–24 months
Proposed COD: 2027-12-31
Cross-source intelligence
Experimental assessment saved at the research date. Predates the Oct 25, 2026 queue source. See the queue record for reported project facts.
Milestones in this assessment
Interconnection Agreement executed per LBNL queue status
Clinton County commissioners formally objected to the proposed 300 MW solar project
wnewsj.comResearch sources and reasoning (1 recorded sources)
low confidence at research time
Commercial operation date: Only LBNL provides a COD target of 2027-12-31. No recent news or press releases confirm or update this timeline. The 2022 news article indicates local opposition but no revised COD.
Developer: LBNL snapshot contains no developer information. News articles and search results did not surface the project developer or operating company name.
Status: LBNL shows 'active' with IA Executed. 2022 news indicates Clinton County commissioners objected to the project, suggesting permitting challenges, but no withdrawal or cancellation announced.
About
Generated Apr 10, 2026 · Predates Oct 25, 2026 queue source
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
The Yellow Wood Solar Energy Center is a proposed 300 MW solar generation project located in Clinton County, Ohio. The project is in the PJM interconnection queue as entry PJM-AE2-221, with a queue entry date of March 21, 2019, and a proposed commercial operation date of December 31, 2027. The interconnection agreement has been executed.
The proposed project has been the subject of recent news coverage, including reports on deals and industry developments.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- PJM queue source as of: Oct 25, 2026.
Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
OH
County
Clinton
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
Dayton
Entity
PJM
Service Type
NRIS
Point of Interconnection
Clinton-Stuart 345 kV
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- PJM
- Trading Hub
- AEP-DAYTON HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Last updated 2026-03-26
View all articlesSolar queue pipeline overview
Summary analysis with parallel narrative sections and visualizations.
Energy Center
Data-driven briefing on Energy Center — fleet, generation, financial, and news signals.
Yellow Wood Solar Energy Center
Data-driven briefing on Yellow Wood Solar Energy Center — fleet, generation, financial, and news signals.
Solar queue pipeline overview
Summary analysis with parallel narrative sections and visualizations.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.