Pilesgrove Solar Project
149.3 MW generation in Salem, NJ · In queue since September 2018 · Proposed COD December 2027
149.3 MW
Capacity
1
Components
Solar
7y 10m
In Queue
IA Executed
IA Phase
COD target: 2027
Total Duration
9y 3m
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Construction pending
Typical: 12–24 months
Proposed COD: 2027-12-31
The Pilesgrove Solar Project is a proposed solar generation project located in Salem County, New Jersey, with a total capacity of 149.3 MW. The project is listed in the PJM interconnection queue as entry AE1-229, with a queue entry date of September 18, 2018. The proposed commercial operation date is December 31, 2027. The interconnection agreement has been executed, but the project is currently listed as suspended.
The project, which is being developed within the PJM region, consists solely of solar photovoltaic generation. The designated point of interconnection is the Deepwater-Upper Pittsgrove 138 kV line.
Generated from interconnection queue and public data sources
Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
NJ
County
Salem
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
AEC
Entity
PJM
Service Type
NRIS
Point of Interconnection
Deepwater-Upper Pittsgrove 138 kV
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- PJM
- Trading Hub
- WESTERN HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Pilesgrove Solar ProjectForward forecasts, scenario decomposition, and risk-decision tooling for this queue project.