Briefing/projectsuspended
Pilesgrove Solar Project is a 149 MW Solar project in New Jersey, currently suspended.
The reported queue phase is IA Executed. Proposed COD is 2027-12-31.
- Queue ID
- PJM-AE1-229
- Location
- Salem, New Jersey
- Technology
- Solar
- Market / region
- PJM
- Point of interconnection
- Deepwater-Upper Pittsgrove 138 kV
What stands out
1
Pilesgrove Solar Project is a 149 MW Solar project in New Jersey with status suspended.
2
The reported queue phase is IA Executed; proposed COD is 2027-12-31.
Market and operating context
- Queue date
- 2018-09-18
- Proposed COD
- 2027-12-31
- IA status
- IA Executed
- Study phase
- IA Executed
- Service type
- NRIS
Why it matters
Queue phase, proposed timing, developer identity, and linked events determine how much of the stated pipeline should be treated as actionable development capacity. The project page and deeper report preserve those fields for further diligence.