Project PacifiCorp-T2-040 — Project Summary

Queue ID
PacifiCorp-T2-040
Capacity
400 MW
Technology
Gas
Status
active
Location
Power, ID
Region
West
Developer
—
IA Status
—

PacifiCorp-T2-040

PacifiCorp-T2-040BetaActiveGasPacifiCorpLBNL

400 MW generation in Power, ID · In queue since September 2025 · Proposed COD October 2031

BA: IPCONERC: WECCRC: RCW

400 MW

Capacity

1

Components

Gas

1y 2m

In Queue

—

IA Status

COD target: 2031

Asset Intelligence Map

One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.

4 live dimensions
4 decision models

Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.

Structured from the current asset record; empty data branches are omitted.Locked nodes are InfraSure decision models; no simulated values shown.
Interconnection

Total Duration

6y 1m

Study Phase

Transition Cluster 2

Pre-Study0%
Queue EntrySep 10, 2025

Interconnection request submitted to ISO/RTO

Interconnection Study

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2031-10-01

About

Saved background

Generated Oct 25, 2026

Figures and claims below reflect the saved summary. See the queue record for reported project facts.

PacifiCorp-T2-040 is a proposed 400 MW natural gas-fired generation project located in Power County, Idaho, in the western United States. The development project consists of a single gas generation component with a capacity of 400 MW. It is listed in the interconnection queue of PacifiCorp, which serves as both the utility and the queue entity for the project. The proposed point of interconnection is the Borah–Populus transmission line.

The project entered PacifiCorp's interconnection queue on September 10, 2025, and its queue status is active. It is being studied as part of PacifiCorp's Transition Cluster 2 study phase and has requested Network Resource Interconnection Service (NRIS). The proposed commercial operation date is October 1, 2031. The available data does not indicate the status of an interconnection agreement for the project.

Summary provenance

Summary generated Oct 25, 2026 (UTC).

Source dates used by this summary were not recorded.

Dates in the current asset record

These may postdate the saved summary; they do not establish which inputs it used.

  • LBNL queue source as of: Dec 31, 2025.
Development Risk

Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.

Available on the InfraSure platform

See the full development-risk decomposition for this project.

P(COD by stated date)
Withdrawal probability vs cohort
IA cluster risk
Project Details

State

ID

County

Power

Grid Region

Mountain West

Market

—

Developer

—

Utility

PacifiCorp

Entity

PacifiCorp

Service Type

NRIS

Point of Interconnection

Borah - Populus transmission line

Data Source

LBNL

Risk Analytics

Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.

Available on the InfraSure platform

See the full risk decomposition + scenarios for this project.

Climate hazards (8+)
Generation variability (P10/P50/P90)
Offtake + transmission counterparty
Generation Forecast

Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.

Available on the InfraSure platform

See the full forecast + scenario decomposition for this project.

P50 conditioned on COD
Capacity factor vs cohort
Weather + policy scenarios
Financial Forecast

Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.

Available on the InfraSure platform

See the full revenue + DSCR projection for this project.

Revenue conditioned on COD
Financing close risk
Cohort DSCR comparison
Market Context
Approximate
ISO / RTO
MOUNTAIN_WEST
Trading Hub
MID-C
Hub Confidence
UNKNOWN

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No insights available for this project.
InfraSure platform

Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.