PacifiCorp-C2-82
300 MW hybrid in Bannock, ID · In queue since May 2022 · Proposed COD December 2027
300 MW
Capacity
1
Components
Solar
4y 6m
In Queue
IA Executed
IA Phase
COD target: 2027
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Total Duration
5y 7m
Study Phase
Cluster 2
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 18–30 months
Proposed COD: 2027-12-31
Cross-source intelligence
Experimental assessment saved at the research date. See the queue record for reported project facts.
Research sources and reasoning (0 recorded sources)
low confidence at research time
No source list recorded with this assessment.
Commercial operation date: Only the LBNL snapshot provides a COD (proposed_cod 2027-12-31). No news or live search findings were available to corroborate or contradict it.
Developer: LBNL lists 'BRP Garnet 1, LLC', which looks like a project shell LLC. No search results were returned to confirm the parent or operating company, so I did not infer one.
Status: LBNL is authoritative on queue state and reports ia_status 'IA Executed' with status 'active'. No newer sources contradict it.
About
Generated Apr 10, 2026
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
PacifiCorp-C2-82 is a proposed 300 MW hybrid solar and battery project located in Bannock County, Idaho. The development project, sponsored by BRP Garnet 1, LLC, consists of 300 MW of solar generation. It is listed in the PacifiCorp interconnection queue as entry C2-82, with a queue entry date of May 12, 2022, and a proposed commercial operation date of December 31, 2027. The interconnection point is the Populus substation, and the project's Interconnection Agreement (IA) has been executed.
The project is currently listed as active in the interconnection queue. Recent news coverage has discussed the project's progress and potential impact on the region's energy infrastructure.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- LBNL queue source as of: Dec 31, 2025.
Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
ID
County
Bannock
Grid Region
Mountain West
Market
—
Developer
BRP Garnet 1, LLC
Utility
PacifiCorp
Entity
PacifiCorp
Service Type
ERIS
Point of Interconnection
Populus substation
Data Source
LBNL
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- MID-C
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.