Resilient NY Energy Storage
349 MW storage in Richmond, NY · In queue since September 2024 · Proposed COD December 2028
349 MW
Capacity
1
Components
Battery
2y 2m
In Queue
—
IA Status
COD target: 2028
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Total Duration
4y 3m
Study Phase
C24
Interconnection request submitted to ISO/RTO
NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.
Typical: >42 months (historical); ~24 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-12-01
Cross-source intelligence
Experimental assessment saved at the research date. See the queue record for reported project facts.
Research sources and reasoning (3 recorded sources)
low confidence at research time
- infrasure.ai/project/nyiso-c24-283-resilient-ny-energy-storage
- interconnection.fyi/project/nyiso-c24-283
- interxdata.com/projects/resilient-ny-energy-storage-nyiso-queue-c24-283/
Commercial operation date: Only the LBNL/NYISO queue date of 2028-12-01 exists. Queue aggregator sites (infrasure.ai, interconnection.fyi) repeat it from the same queue data and add no independent developer-backed target.
Developer: The LBNL filing entity is the project LLC, managed by Hanwha Energy USA Holdings Corporation, which is named as manager in the filing and repeated in the infrasure.ai summary. No press release independently confirms the relationship, and no ownership change was found.
Status: LBNL and aggregator sites (infrasure.ai, interxdata.com) show the project as active with no IA executed. No news shows construction, permitting, or withdrawal.
About
Generated Apr 10, 2026 · Predates Sep 30, 2026 queue source
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
The Resilient NY Energy Storage project is a proposed 349 MW battery storage project located in Richmond County, New York. The developer is Resilient NY Storage, LLC, managed by Hanwha Energy USA Holdings Corporation. Interconnection is requested with Consolidated Edison (ConEd) at the Goethals 345 kV point of interconnection.
The project is listed in the New York Independent System Operator (NYISO) interconnection queue as entry NYISO-C24-283, with a queue entry date of September 25, 2024. The proposed commercial operation date is December 1, 2028. The project is currently listed as active in the interconnection queue.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- NYISO queue source as of: Sep 30, 2026.
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
NY
County
Richmond
Grid Region
NYISO (New York)
Market
ISO/RTO Member
Developer
Resilient NY Storage, LLC by Hanwha Energy USA Holdings Corporation, its Manager
Utility
ConEd
Entity
NYISO
Service Type
—
Point of Interconnection
Goethals 345 kV
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- NYISO
- Trading Hub
- ZONE J
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- PJM_GEN_VFT_PROXY
- POI Substation
- Goethals Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
KCE NY 2
Cross-dimensional entity briefing with KPIs, news intelligence, and fleet analysis.
KCE NY 31
Cross-dimensional entity briefing with KPIs, news intelligence, and fleet analysis.
Battery storage queue pipeline
Summary analysis with parallel narrative sections and visualizations.
KCE NY 21
Cross-dimensional entity briefing with KPIs, news intelligence, and fleet analysis.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.