Stargazer I
325 MW hybrid in Mckean, PA · In queue since September 2024 · Proposed COD July 2029
325 MW
Capacity
1
Components
Solar
1y 10m
In Queue
—
IA Status
COD target: 2029
Total Duration
4y 10m
Study Phase
C24
Interconnection request submitted to ISO/RTO
NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.
Typical: >42 months (historical); ~24 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2029-07-01
NYISO queue entry submitted for 325 MW solar+storage project
Stargazer I is a proposed 325 MW hybrid solar and battery energy storage project located in McKean County, Pennsylvania. Developed by RWE Solar Development, LLC, the project consists of 325 MW of solar generation. It is interconnected to the NYISO grid via the Homer City to Pierce Brook 345 kV Line and is in the NYISO interconnection queue as entry NYISO-C24-175, filed on September 17, 2024.
The proposed commercial operation date for Stargazer I is December 1, 2027. The project is currently listed as active in the interconnection queue.
Generated from interconnection queue and public data sources
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
PA
County
Mckean
Grid Region
NYISO (New York)
Market
ISO/RTO Member
Developer
RWE Solar Development, LLC
Utility
NYSEG
Entity
NYISO
Service Type
—
Point of Interconnection
Homer City to Pierce Brook 345 kV Line
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- NYISO
- Trading Hub
- ZONE F
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Stargazer IForward forecasts, scenario decomposition, and risk-decision tooling for this queue project.