Stargazer I (NYISO-C24-175) — Project Summary

Queue ID
NYISO-C24-175
Capacity
325 MW
Technology
Solar+Battery
Status
active
Location
Mckean, PA
Region
NYISO
Developer
RWE Solar Development, LLC
IA Status
—

Stargazer I

NYISO-C24-175BetaActiveSolarBatteryNYISOLBNL + Live

325 MW hybrid in Mckean, PA · In queue since September 2024 · Proposed COD July 2029

BA: PJMISO/RTO: NYISONERC: RFCRC: PJM

325 MW

Capacity

1

Components

Solar

2y 2m

In Queue

—

IA Status

COD target: 2029

Asset Intelligence Map

One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.

5 live dimensions
4 decision models

Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.

Structured from the current asset record; empty data branches are omitted.Locked nodes are InfraSure decision models; no simulated values shown.
Interconnection

Total Duration

4y 10m

Study Phase

C24

Pre-Study0%
Queue EntrySep 17, 2024

Interconnection request submitted to ISO/RTO

TCS Study

NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.

Typical: >42 months (historical); ~24 months target

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2029-07-01

Cross-source intelligence

Saved research · Beta
Researched Oct 25, 2026

Experimental assessment saved at the research date. See the queue record for reported project facts.

Research COD
Jul 1, 2029
From queue filing
Developer in saved assessment
RWE
Filed as RWE Solar Development, LLC
Status at research time
Active
Active in NYISO queue (C24-175); project still in development, no construction start announced; local opposition and permitting activity in McKean County, PA
Financing
Not recorded
Research sources and reasoning (5 recorded sources)

medium confidence at research time

  1. americas.rwe.com/our-energy/solar-energy/solar-projects-and-locations/stargazer-solar/
  2. interconnection.fyi/project/nyiso-c24-175
  3. interxdata.com/projects/stargazer-i-nyiso-queue-c24-175/
  4. protectmckeancountywilds.com/rwe-stargazer.html
  5. infrasure.ai/project/nyiso-c24-175-stargazer-i

Commercial operation date: No developer press release or news item gives a construction-backed COD. Aggregators (interconnection.fyi, interxdata) only restate the NYISO queue date (June 30 / July 1, 2029), and RWE's project page says only 'In development'.

Developer: The LBNL filing entity is RWE Solar Development, LLC. RWE Americas' project page says 'RWE will own, build, and operate the project', so the operating parent is RWE.

Status: LBNL and aggregators list the project as active. RWE's page lists status as 'In development', with no IA, construction or withdrawal signal.

About

Saved background

Generated Apr 10, 2026 · Predates Sep 30, 2026 queue source

Figures and claims below reflect the saved summary. See the queue record for reported project facts.

Stargazer I is a proposed 325 MW hybrid solar and battery energy storage project located in McKean County, Pennsylvania. Developed by RWE Solar Development, LLC, the project consists of 325 MW of solar generation. It is interconnected to the NYISO grid via the Homer City to Pierce Brook 345 kV Line and is in the NYISO interconnection queue as entry NYISO-C24-175, filed on September 17, 2024.

The proposed commercial operation date for Stargazer I is December 1, 2027. The project is currently listed as active in the interconnection queue.

Summary provenance

Summary generated Apr 10, 2026 (UTC).

Source dates used by this summary were not recorded.

Dates in the current asset record

These may postdate the saved summary; they do not establish which inputs it used.

  • NYISO queue source as of: Sep 30, 2026.
Development Risk

Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.

Available on the InfraSure platform

See the full development-risk decomposition for this project.

P(COD by stated date)
Withdrawal probability vs cohort
IA cluster risk
Project Details

State

PA

County

Mckean

Grid Region

NYISO (New York)

Market

ISO/RTO Member

Developer

RWE Solar Development, LLC

Utility

NYSEG

Entity

NYISO

Service Type

—

Point of Interconnection

Homer City to Pierce Brook 345 kV Line

Data Source

LBNL + Live

Risk Analytics

Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.

Available on the InfraSure platform

See the full risk decomposition + scenarios for this project.

Climate hazards (8+)
Generation variability (P10/P50/P90)
Offtake + transmission counterparty
Generation Forecast

Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.

Available on the InfraSure platform

See the full forecast + scenario decomposition for this project.

P50 conditioned on COD
Capacity factor vs cohort
Weather + policy scenarios
Financial Forecast

Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.

Available on the InfraSure platform

See the full revenue + DSCR projection for this project.

Revenue conditioned on COD
Financing close risk
Cohort DSCR comparison
Market Context
Approximate
ISO / RTO
NYISO
Trading Hub
ZONE F
Hub Confidence
MEDIUM

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No insights available for this project.
InfraSure platform

Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.