74.5 MW generation in Knox, ME · In queue since November 2020 · Proposed COD November 2026
74.5 MW
Capacity
1
Components
Solar
5y 8m
In Queue
IA Executed
IA Phase
COD target: 2026
Total Duration
6 years
Interconnection request submitted to ISO/RTO
ISO-NE is transitioning to cluster studies per FERC Order 2023.
Typical: 25–30 months (recent)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–24 months
Proposed COD: 2026-11-30
Warren Meadow Solar is a proposed 74.5 MW solar generation project located in Knox County, Maine. The project is listed in the ISO-NE interconnection queue as queue ID 1086, with an entry date of November 30, 2020, and a proposed commercial operation date of November 30, 2026. The interconnection agreement for the project has been executed.
The proposed project is linked to the existing Warren Meadow Solar Station operating plant (EIA ID 65708). The project has appeared in recent news coverage.
Generated from interconnection queue and public data sources
Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
ME
County
Knox
Grid Region
ISO New England
Market
ISO/RTO Member
Developer
—
Utility
—
Entity
ISO-NE
Service Type
ERIS
Point of Interconnection
CMP 115kV line Section 80
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ISO-NE
- Trading Hub
- .Z.MAINE
- Hub Confidence
- MEDIUM
- Nearest Node (Estimated)
- LD.HIGHLAND34.5
- POI Substation
- Highland Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Warren Meadow SolarForward forecasts, scenario decomposition, and risk-decision tooling for this queue project.