IP-725
175 MW hybrid in Bingham, ID · In queue since June 2023 · Proposed COD June 2027
175 MW
Capacity
1
Components
Solar
3y 1m
In Queue
Cluster Study
IA Phase
COD target: 2027
Total Duration
4 years
Study Phase
Transitional Cluster
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-06-01
IP-725 is a proposed 175 MW hybrid solar and battery project located in Bingham County, Idaho. The project, which consists of 175 MW of solar capacity, is interconnected to the Idaho Power Company (IP) grid at the Brady-Antelope 230kV Line.
The project is listed in the IP interconnection queue as of June 12, 2023, with a proposed commercial operation date of June 1, 2027. The interconnection agreement (IA) for the project has been executed, with the IA date listed as December 31, 1999.
Generated from interconnection queue and public data sources
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
ID
County
Bingham
Grid Region
Mountain West
Market
—
Developer
—
Utility
Idaho Power Company
Entity
IP
Service Type
NRIS
Point of Interconnection
Brady-Antelope 230kV Line
Data Source
LBNL
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- MID-C
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Project IP-725Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.