IP-665
400 MW hybrid in Ada, ID · In queue since August 2022 · Proposed COD June 2027
400 MW
Capacity
1
Components
Solar
3y 11m
In Queue
IA Executed
IA Phase
Signed Apr 2024
Queue → IA
1y 8m
IA → COD
3y 2m
Total Duration
1y 8m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 18–30 months
Proposed COD: 2027-06-01
Interconnection Agreement executed per LBNL queue data
IP-665 is a proposed 400 MW solar and battery hybrid project located in Ada County, Idaho. The development project, under the name Blacks Creek Energy Center, LLC, is interconnected with Idaho Power Company (IP). The project consists of 400 MW of solar capacity.
The project is listed as active in the IP interconnection queue, with an entry date of August 16, 2022, and a proposed commercial operation date of December 31, 2027. The interconnection agreement (IA) was executed on April 4, 2024. The point of interconnection is the BOBN_x0013_Hubbard 230kV Line.
Generated from interconnection queue and public data sources
Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
ID
County
Ada
Grid Region
Mountain West
Market
—
Developer
Blacks Creek Energy Center, LLC
Utility
Idaho Power Company
Entity
IP
Service Type
NRIS
Point of Interconnection
BOBN–Hubbard 230kV Line
Data Source
LBNL
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- MID-C
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Project IP-665Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.