IP-655
325 MW hybrid in Bear Lake, ID · In queue since May 2022 · Proposed COD September 2026
325 MW
Capacity
1
Components
Solar
4y 2m
In Queue
IA Executed
IA Phase
Signed Dec 2023
Queue → IA
1y 7m
IA → COD
2y 9m
Total Duration
1y 7m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Construction pending
Typical: 18–30 months
Proposed COD: 2026-09-01
The proposed IP-655 project is a 325 MW solar and battery hybrid development located in Bear Lake County, Idaho. Being developed by Aurora Solar LLC, the project consists of 325 MW of solar capacity. It is interconnected to the Idaho Power Company grid at the Bridger_x0013_Populus 345kV Line.
The project is listed in the IP (Idaho Power) interconnection queue with an entry date of May 10, 2022, and a proposed commercial operation date of December 31, 2025. An Interconnection Agreement (IA) for the project was executed on December 14, 2023. The project's interconnection status is listed as active.
Generated from interconnection queue and public data sources
Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
ID
County
Bear Lake
Grid Region
Mountain West
Market
—
Developer
Aurora Solar LLC
Utility
Idaho Power Company
Entity
IP
Service Type
ERIS
Point of Interconnection
Bridger–Populus 345kV Line
Data Source
LBNL
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- MID-C
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.