IP-636
149 MW generation in Elmore, ID · In queue since February 2022 · Proposed COD April 2028
149 MW
Capacity
1
Components
Solar
4y 5m
In Queue
IA Executed
IA Phase
Signed Mar 2024
Queue → IA
2y 1m
IA → COD
4y 1m
Total Duration
2y 1m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–24 months
Proposed COD: 2028-04-01
Interconnection Agreement executed with Idaho Power
Proposed commercial operation date per LBNL queue
IP-636 is a proposed solar generation project with a total capacity of 149 MW, located in Elmore County, Idaho. The developer is Soles Rest Solar LLC. The project is interconnected with Idaho Power Company (IP) and is in the IP interconnection queue, with an entry date of February 16, 2022. The proposed commercial operation date is December 31, 2025.
The project's interconnection agreement (IA) has been executed as of March 13, 2024. The point of interconnection (POI) is the Danskin_x0013_Hubbard 230kV Line. The project has appeared in recent news coverage.
Generated from interconnection queue and public data sources
Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
ID
County
Elmore
Grid Region
Mountain West
Market
—
Developer
Soles Rest Solar LLC
Utility
Idaho Power Company
Entity
IP
Service Type
NRIS
Point of Interconnection
Danskin–Hubbard 230kV Line
Data Source
LBNL
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- MID-C
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Project IP-636Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.