IP-634
13 MW storage in Owyhee, ID · In queue since January 2022 · Proposed COD June 2024
13 MW
Capacity
1
Components
Battery
4y 6m
In Queue
IA Executed
IA Phase
Signed Jan 2023
Queue → IA
1 year
IA → COD
1y 5m
Total Duration
1 year
Schedule
26 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 6–18 months
Proposed COD: 2024-06-01
IP-634 is a proposed 13 MW battery storage project located in Owyhee County, Idaho. The project is being developed by Idaho Power Company_x0014_Power Supply and is interconnected to the Idaho Power Company utility grid at the Hemingway 34.5kV point of interconnection.
The project is listed in the IP (Idaho Power) interconnection queue with an entry date of January 25, 2022, and a proposed commercial operation date of June 1, 2024. The interconnection agreement for the project was executed on January 20, 2023.
Generated from interconnection queue and public data sources
Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
ID
County
Owyhee
Grid Region
Mountain West
Market
—
Developer
Idaho Power Company—Power Supply
Utility
Idaho Power Company
Entity
IP
Service Type
NRIS
Point of Interconnection
Hemingway 34.5kV
Data Source
LBNL
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- MID-C
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Project IP-634Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.