Project IP-604 — Project Summary

Queue ID
IP-604
Capacity
100 MW
Technology
Solar+Battery
Status
active
Location
Elmore, ID
Region
West
Developer
Crimson Orchard Solar LLC
IA Status
IA Executed

IP-604

IP-604BetaActiveSolarBatteryIPLBNL

100 MW hybrid in Elmore, ID · In queue since May 2021 · Proposed COD June 2026

BA: IPCONERC: WECCRC: RCW

100 MW

Capacity

1

Components

Solar

5y 2m

In Queue

IA Executed

IA Phase

Signed Jan 2023

Interconnection

Queue → IA

1y 8m

IA → COD

3y 5m

Total Duration

1y 8m

Schedule

1 months past proposed COD

Construction75%
Queue EntryMay 27, 2021

Interconnection request submitted to ISO/RTO

Interconnection Study

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection AgreementJan 24, 2023

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 18–30 months

Commercial Operation

Proposed COD: 2026-06-01

Cross-source intelligence
Beta
Low confidence·0 sources·as of 2026-06-01
Expected COD
2026-06-01
From queue filing
Developer
Crimson Orchard Solar LLC
From queue filing
Status
Active
Active — IA executed January 2023, no public updates on construction timeline
Financing
Unannounced
Key milestones
IA executedJan 24, 2023Most recent

Interconnection Agreement executed per LBNL queue data

About

The proposed IP-604 project is a 100 MW solar and battery hybrid development in Elmore County, Idaho. The project, developed by Crimson Orchard Solar LLC, consists of 100 MW of solar capacity. It is interconnected to the Idaho Power Company via the Danskin 230kV Substation.

The project is listed in the IP interconnection queue with an entry date of May 27, 2021, and a proposed commercial operation date of December 1, 2024. The interconnection agreement was executed on January 24, 2023. The project is currently listed as active in the queue.

Generated from interconnection queue and public data sources

Development Risk

Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.

Available on the InfraSure platform

See the full development-risk decomposition for this project.

P(COD by stated date)
Financing close probability
EPC + tax-equity counterparty
Project Details

State

ID

County

Elmore

Grid Region

Mountain West

Market

Developer

Crimson Orchard Solar LLC

Utility

Idaho Power Company

Entity

IP

Service Type

NRIS

Point of Interconnection

Danskin 230kV Substation

Data Source

LBNL

Risk Analytics

Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.

Available on the InfraSure platform

See the full risk decomposition + scenarios for this project.

Climate hazards (8+)
Generation variability (P10/P50/P90)
Offtake + transmission counterparty
Generation Forecast

Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.

Available on the InfraSure platform

See the full forecast + scenario decomposition for this project.

10-year P50 forecast
First-year output estimate
Weather + policy scenarios
Financial Forecast

Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.

Available on the InfraSure platform

See the full revenue + DSCR projection for this project.

10-year revenue projection
First-year DSCR
Financing close risk
Market Context
Approximate
ISO / RTO
MOUNTAIN_WEST
Trading Hub
MID-C
Hub Confidence
UNKNOWN

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No insights available for this project.