IP-588
125 MW generation in Ada, ID · In queue since September 2020 · Proposed COD April 2026
125 MW
Capacity
1
Components
Solar
6y 2m
In Queue
IA Executed
IA Phase
Signed Sep 2022
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Queue → IA
2 years
IA → COD
3y 7m
Total Duration
2 years
Schedule
7 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–24 months
Proposed COD: 2026-04-15
Cross-source intelligence
Experimental assessment saved at the research date. See the queue record for reported project facts.
Milestones in this assessment
Interconnection Agreement executed per LBNL queue data
Research sources and reasoning (0 recorded sources)
low confidence at research time
No source list recorded with this assessment.
Commercial operation date: Only LBNL queue data available with proposed COD of April 2026. No independent news or research sources to validate or contradict this date.
Developer: Only LBNL filing entity 'PVS 2, LLC' is known. No research available to identify parent company or operating entity behind this project LLC.
Status: LBNL shows active status with interconnection agreement executed in 2022, indicating project has secured queue position and interconnection rights.
About
Generated Apr 10, 2026
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
IP-588 is a proposed solar generation project located in Ada County, Idaho, with a total capacity of 125 MW. The project, developed by PVS 2, LLC, is interconnected to the Idaho Power Company grid. It entered the IP interconnection queue on September 10, 2020, with a proposed commercial operation date of October 1, 2024.
The project's Interconnection Agreement (IA) was executed on September 14, 2022, and its current status is listed as active. The point of interconnection (POI) is Hubbard_x0013_Danskin 230kV.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- LBNL queue source as of: Dec 31, 2025.
Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
ID
County
Ada
Grid Region
Mountain West
Market
—
Developer
PVS 2, LLC
Utility
Idaho Power Company
Entity
IP
Service Type
NRIS
Point of Interconnection
Hubbard–Danskin 230kV
Data Source
LBNL
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- MID-C
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.