Rebecca Solar
120 MW generation in Turner, GA · In queue since December 2024 · Proposed COD December 2028
120 MW
Capacity
1
Components
Solar
1y 7m
In Queue
System Impact Study
IA Phase
COD target: 2028
Total Duration
4 years
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-12-01
Entered GTC queue for System Impact Study
The Rebecca Solar project is a proposed 120 MW solar generation facility in Turner County, Georgia. The project is being developed within the Georgia Transmission (GTC) interconnection queue, identified as GTC-GI-199, with a queue entry date of December 11, 2024. The proposed commercial operation date is December 1, 2028.
The interconnection agreement (IA) for Rebecca Solar is currently listed as "In Progress (unknown study)". The point of interconnection (POI) is the North Tifton - Pitts 230 kV line. The project has been mentioned in recent industry news.
Generated from interconnection queue and public data sources
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
GA
County
Turner
Grid Region
Southeast
Market
—
Developer
—
Utility
Georgia Transmission
Entity
GTC
Service Type
—
Point of Interconnection
North Tifton - Pitts 230 kV line
Data Source
LBNL
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- SOUTHEAST
- Trading Hub
- Southern Company
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Rebecca SolarForward forecasts, scenario decomposition, and risk-decision tooling for this queue project.