Flint River 780 MW Unit (GTC-GI-198) — Project Summary

Queue ID
GTC-GI-198
Capacity
780 MW
Technology
Gas
Status
active
Location
Mitchell, GA
Region
Southeast
Developer
—
IA Status
System Impact Study

Flint River 780 MW Unit

GTC-GI-198BetaActiveGasGTCLBNL

780 MW generation in Mitchell, GA · In queue since October 2024 · Proposed COD August 2029

BA: SOCONERC: SERCRC: SOCO

780 MW

Capacity

1

Components

Gas

2y 1m

In Queue

System Impact Study

IA Phase

COD target: 2029

Asset Intelligence Map

One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.

5 live dimensions
4 decision models

Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.

Structured from the current asset record; empty data branches are omitted.Locked nodes are InfraSure decision models; no simulated values shown.
Interconnection

Total Duration

4y 10m

Impact Study25%
Queue EntryOct 9, 2024

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2029-08-01

Cross-source intelligence

Saved research · Beta
Researched Oct 25, 2026

Experimental assessment saved at the research date. See the queue record for reported project facts.

Research COD
Aug 1, 2029
From queue filing
Developer in saved assessment
—
Status at research time
Active
Active in Georgia Transmission queue, in System Impact Study phase; no IA executed, POI at Raccoon Creek Substation; no public evidence of construction or financing.
Financing
Not recorded
Research sources and reasoning (3 recorded sources)

low confidence at research time

  1. infrasure.ai/project/gtc-gi-198-flint-river-780-mw-unit
  2. interconnection.fyi/project/georgia-transmission-gi-198
  3. app.nrgmap.com/queues/lbnl-gtc-gi-198

Commercial operation date: Only queue-derived sources exist; the infrasure.ai listing says 'Proposed COD: 2029-08-01' and interconnection.fyi says July 31, 2029. Both are aggregators of the LBNL/GTC data, not independent developer confirmation.

Developer: LBNL developer field is null and no search result names a developer or parent company for GTC-GI-198.

Status: LBNL lists status active and NRG Map shows active as of 31 Dec 2025. Infrasure confirms System Impact Study with no executed interconnection agreement.

About

Saved background

Generated Apr 10, 2026

Figures and claims below reflect the saved summary. See the queue record for reported project facts.

The proposed Flint River 780 MW Unit is a gas-fired generation project located in Mitchell County, Georgia. The project, with a total capacity of 780 MW of gas generation, is being developed within the Georgia Transmission (GTC) service area.

The project is listed in the Georgia Transmission queue as GTC-GI-198, with an interconnection queue entry date of October 9, 2024. The proposed commercial operation date is August 1, 2029. The project's interconnection status is currently in the System Impact Study phase and the point of interconnection is the Raccoon Creek Substation.

Summary provenance

Summary generated Apr 10, 2026 (UTC).

Source dates used by this summary were not recorded.

Dates in the current asset record

These may postdate the saved summary; they do not establish which inputs it used.

  • LBNL queue source as of: Dec 31, 2025.
Development Risk

Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.

Available on the InfraSure platform

See the full development-risk decomposition for this project.

P(COD by stated date)
Withdrawal probability vs cohort
IA cluster risk
Project Details

State

GA

County

Mitchell

Grid Region

Southeast

Market

—

Developer

—

Utility

Georgia Transmission

Entity

GTC

Service Type

—

Point of Interconnection

Raccoon Creek Substation

Data Source

LBNL

Risk Analytics

Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.

Available on the InfraSure platform

See the full risk decomposition + scenarios for this project.

Climate hazards (8+)
Generation variability (P10/P50/P90)
Offtake + transmission counterparty
Generation Forecast

Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.

Available on the InfraSure platform

See the full forecast + scenario decomposition for this project.

P50 conditioned on COD
Capacity factor vs cohort
Weather + policy scenarios
Financial Forecast

Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.

Available on the InfraSure platform

See the full revenue + DSCR projection for this project.

Revenue conditioned on COD
Financing close risk
Cohort DSCR comparison
Market Context
Approximate
ISO / RTO
SOUTHEAST
Trading Hub
Southern Company
Hub Confidence
UNKNOWN

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No insights available for this project.
InfraSure platform

Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.