Red Dirt Solar
153 MW hybrid in Talbot, GA · In queue since April 2023 · Proposed COD September 2026
153 MW
Capacity
1
Components
Solar
3y 3m
In Queue
Facility Study
IA Phase
COD target: 2026
Total Duration
3y 5m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-09-30
Entered Georgia Transmission queue as GTC-GI-172
Proposed commercial operation date per LBNL queue filing
Red Dirt Solar is a proposed 153 MW hybrid solar and battery energy storage project located in Talbot County, Georgia. The development project consists of 153 MW of solar photovoltaic generation. It is interconnected to the Georgia Transmission Corporation (GTC) system and is listed in the GTC interconnection queue as project GTC-GI-172. The project entered the queue on April 6, 2023, with a proposed commercial operation date of September 30, 2026. Its interconnection agreement status is currently in the Facility Study phase.
The Red Dirt Solar project has been the subject of recent news coverage, with four articles published related to the industry and regulatory aspects of the project.
Generated from interconnection queue and public data sources
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
GA
County
Talbot
Grid Region
Southeast
Market
—
Developer
—
Utility
Georgia Transmission
Entity
GTC
Service Type
—
Point of Interconnection
Patsiliga Creek - Talbot County #1 230 kV
Data Source
LBNL
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- SOUTHEAST
- Trading Hub
- Southern Company
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Red Dirt SolarForward forecasts, scenario decomposition, and risk-decision tooling for this queue project.