SR Rochelle Solar
120 MW generation in Wilcox, GA · In queue since December 2021 · Proposed COD December 2026
120 MW
Capacity
1
Components
Solar
4y 7m
In Queue
Construction
IA Phase
COD target: 2026
Total Duration
5 years
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-12-31
The SR Rochelle Solar project is a proposed 120 MW solar generation project located in Wilcox County, Georgia. The project is listed in the Georgia Transmission Corporation (GTC) interconnection queue as entry GTC-GI-158, with a queue entry date of December 9, 2021. The proposed commercial operation date is November 1, 2026, and the project's interconnection agreement status is currently listed as "Construction".
The project connects to the Fitzgerald - Pitts 115 kV transmission line. Recent news coverage has discussed the development project.
Generated from interconnection queue and public data sources
Realization risk through commissioning — schedule slippage, construction cost overrun, and COD probability vs the stated window. The diligence view that determines whether the project comes online when promised. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
GA
County
Wilcox
Grid Region
Southeast
Market
—
Developer
—
Utility
Georgia Transmission
Entity
GTC
Service Type
—
Point of Interconnection
Fitzgerald - Pitts 115 kV TL
Data Source
LBNL
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with curtailment risk decomposed by congestion zone and ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, first-year DSCR, and construction cost overrun exposure — what determines whether the deal clears its covenants once online. Projected across price, demand, and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- SOUTHEAST
- Trading Hub
- Southern Company
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about SR Rochelle SolarForward forecasts, scenario decomposition, and risk-decision tooling for this queue project.