Briefing/projectactive
SR Rochelle Solar is a 120 MW Solar project in Georgia, currently active.
The reported queue phase is Construction. Proposed COD is 2026-12-31.
- Queue ID
- GTC-GI-158
- Location
- Wilcox, Georgia
- Technology
- Solar
- Market / region
- Southeast
- Point of interconnection
- Fitzgerald - Pitts 115 kV TL
What stands out
1
SR Rochelle Solar is a 120 MW Solar project in Georgia with status active.
2
The reported queue phase is Construction; proposed COD is 2026-12-31.
Market and operating context
- Queue date
- 2021-12-09
- Proposed COD
- 2026-12-31
- IA status
- Construction
- Study phase
- Construction
Why it matters
Queue phase, proposed timing, developer identity, and linked events determine how much of the stated pipeline should be treated as actionable development capacity. The project page and deeper report preserve those fields for further diligence.