Dellwood Solar
150 MW hybrid in Emanuel, GA · In queue since May 2021 · Proposed COD February 2024
150 MW
Capacity
1
Components
Solar
5y 2m
In Queue
Facility Study
IA Phase
COD target: 2024
Total Duration
2y 9m
Schedule
29 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2024-02-28
Entered GTC queue at Facility Study stage
Proposed commercial operation date per LBNL queue
The Dellwood Solar project is a proposed 150 MW hybrid solar and battery energy storage project located in Emanuel County, Georgia. Interconnecting to the Georgia Transmission (GTC) grid at the Vidalia-Wadley Primary (white) 230 kV line, the project entered the GTC interconnection queue (GTC-GI-149) on May 4, 2021. The proposed commercial operation date is February 28, 2024, and the project's interconnection status is currently in the Facility Study phase.
The development project consists of 150 MW of solar photovoltaic generation capacity. It is listed as an active project in the interconnection queue. The developer is not specified in the available data, but the project has appeared in recent news coverage regarding renewable energy development in the Southeast region.
Generated from interconnection queue and public data sources
Realization history for this asset — final cost vs plan, COD slip vs original date, and construction duration vs cohort. Retrospective context for the operating risk view above. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
GA
County
Emanuel
Grid Region
Southeast
Market
—
Developer
—
Utility
Georgia Transmission
Entity
GTC
Service Type
—
Point of Interconnection
Vidalia-Wadley Primary (white) 230 kV line
Data Source
LBNL
Composite operating risk view for this asset — climate hazards across its remaining operating life, observed generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — 10-year P50 trajectory accounting for degradation, observed curtailment, and market conditions, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR bands, and refinancing risk for this asset — 10-year cashflow projected under price, demand, and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- SOUTHEAST
- Trading Hub
- Southern Company
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.