Bear Bin Solar
150 MW generation in Terrell, GA · In queue since October 2019 · Proposed COD December 2023
150 MW
Capacity
1
Components
Solar
6y 9m
In Queue
Facility Study
IA Phase
COD target: 2023
Total Duration
4y 2m
Schedule
31 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2023-12-31
Bear Bin Solar is a proposed 150 MW solar generation project located in Terrell County, Georgia. The project is being developed within the Georgia Transmission (GTC) interconnection queue as project GTC-GI-125. The queue entry date is October 4, 2019, and the proposed commercial operation date is December 31, 2023.
The project's interconnection status is currently in the Facility Study phase. The point of interconnection is the Walk Ikey Creek 115 kV SS. The project has appeared in recent news.
Generated from interconnection queue and public data sources
Realization history for this asset — final cost vs plan, COD slip vs original date, and construction duration vs cohort. Retrospective context for the operating risk view above. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
GA
County
Terrell
Grid Region
Southeast
Market
—
Developer
—
Utility
Georgia Transmission
Entity
GTC
Service Type
—
Point of Interconnection
Walk Ikey Creek 115 kV SS
Data Source
LBNL
Composite operating risk view for this asset — climate hazards across its remaining operating life, observed generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — 10-year P50 trajectory accounting for degradation, observed curtailment, and market conditions, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR bands, and refinancing risk for this asset — 10-year cashflow projected under price, demand, and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- SOUTHEAST
- Trading Hub
- Southern Company
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Bear Bin SolarForward forecasts, scenario decomposition, and risk-decision tooling for this queue project.