GrantPUD-7
200 MW generation in Grant, WA · In queue since September 2020
200 MW
Capacity
1
Components
Solar
5y 10m
In Queue
Facility Study
IA Phase
Total Duration
5y 10m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial operation date not yet determined
GrantPUD-7 is a proposed 200 MW solar generation project located in Grant County, Washington. The project is being developed by GrantPUD and is interconnected to the Columbia - Rocky Ford 230 kV line. It entered the Grant County Public Utility District interconnection queue on September 4, 2020. The project's interconnection status is currently in the System Impact Study phase.
The proposed project consists of 200 MW of solar photovoltaic generation. It is listed as active in the interconnection queue.
Generated from interconnection queue and public data sources
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
WA
County
Grant
Grid Region
Mountain West
Market
—
Developer
—
Utility
Grant County Public Utility District
Entity
GrantPUD
Service Type
—
Point of Interconnection
Columbia - Rocky Ford 230 kV line
Data Source
LBNL
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- MID-C
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Project GrantPUD-7Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.