SIM GIDEON GAS RICE
226.03 MW generation in Bastrop, TX · In queue since July 2025 · Proposed COD May 2031
226.03 MW
Capacity
1
Components
Gas
1y 4m
In Queue
Facility Study
IA Phase
COD target: 2031
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Total Duration
5y 10m
Interconnection request submitted to ISO/RTO
SS Completed, FIS Started, IA
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2031-05-10
Projected COD moved
0 times
May 2031 → May 2031
Net change
0 months
first report to latest
Capacity
226 MW
unchanged in the reports
Latest stage
IA signed
in ERCOT's latest report
Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).
Cross-source intelligence
Experimental assessment saved at the research date. Predates the Oct 1, 2026 queue source. See the queue record for reported project facts.
Milestones in this assessment
Entered ERCOT interconnection queue, Facility Study phase
Proposed commercial operation date per ERCOT filing
Research sources and reasoning (0 recorded sources)
low confidence at research time
No source list recorded with this assessment.
Commercial operation date: Only LBNL queue data available with proposed COD of May 2031. No independent news or press releases found to validate or contradict this date.
Developer: LBNL lists LCRA (Lower Colorado River Authority) as developer. LCRA is a public utility authority, not a shell LLC, so this appears to be the actual operating entity. No news coverage found to confirm or provide additional detail.
Status: LBNL status shows 'active' with Facility Study in progress. Queue date of July 2025 indicates very recent entry into interconnection process.
About
Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
The SIM GIDEON GAS RICE project is a proposed 226.03 MW gas-fired generation project located in Bastrop County, Texas. The project, being developed by LCRA, consists of internal combustion technology and is listed in the ERCOT interconnection queue as entry ERCOT-31INR0011, with a queue entry date of July 29, 2025. The proposed commercial operation date is May 10, 2031.
This project is currently active in the ERCOT queue. Interconnection will be at the (#7310) SIM GIDEON 138 kV point of interconnection. The SIM GIDEON GAS RICE project has been the subject of recent news coverage related to regulatory matters.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- ERCOT queue source as of: Oct 1, 2026.
- Queue history observations through: Sep 2026.
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Bastrop
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
LCRA
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
(#7310) SIM GIDEON 138 kV
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_SOUTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.