Prairie Ridge (Gas - CC)
1,660.4 MW generation in Franklin, TX · In queue since December 2025 · Proposed COD June 2032
1,660.4 MW
Capacity
1
Components
Gas
11 months
In Queue
Facility Study
IA Phase
COD target: 2032
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Total Duration
6y 6m
Interconnection request submitted to ISO/RTO
SS Completed, FIS Started, No IA
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2032-06-01
Projected COD moved
0 times
Jun 2032 → Jun 2032
Net change
0 months
first report to latest
Capacity
1660 MW
unchanged in the reports
Latest stage
Screening started
in ERCOT's latest report
Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).
Cross-source intelligence
Experimental assessment saved at the research date. See the queue record for reported project facts.
Research sources and reasoning (6 recorded sources)
low confidence at research time
- interconnection.fyi/project/ercot-30inr0071
- ercotqueue.com/project/30INR0071
- app.nrgmap.com/queues/ercot-30inr0071
- infrasure.ai/project/ercot-30inr0071-prairie-ridge-gas-cc
- cleanview.co/power-projects/planned/natural-gas-power-plants/texas/30INR0071/prairie-ridge-gas---cc
- tenaska.com/our-expertise/generation/
Commercial operation date: Only queue-derived sources exist. Cleanview and interconnection.fyi both repeat the LBNL/ERCOT proposed date (2032, June 1, 2032), so they are not independent. No developer press release or news article gives a different target.
Developer: Queue aggregators (infrasure.ai, ercotqueue.com, interconnection.fyi) all repeat the LBNL filing entity. Tenaska's own site shows it as a generation owner/developer, but no source mentions Prairie Ridge, so the parent relationship is unconfirmed.
Status: LBNL lists status as active and NRG Map shows active as of 1 September 2026. No source reports permits, financing, or construction, so the project is still at an early study stage.
About
Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
The Prairie Ridge (Gas - CC) project is a proposed 1660.4 MW natural gas combined-cycle generation project located in Franklin County, Texas. The project is being developed by Tenaska Power Generation, LLC. It is listed in the ERCOT interconnection queue as entry ERCOT-30INR0071, with a queue entry date of December 1, 2025. The proposed commercial operation date is June 1, 2032.
The point of interconnection (POI) for the project is the TAP 345 KV line between substations 11699 WOODARD and 11702 BEARPEN. The project currently has an active status within the ERCOT interconnection queue.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- ERCOT queue source as of: Oct 1, 2026.
- Queue history observations through: Sep 2026.
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Franklin
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Tenaska Power Generation, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
TAP 345 KV 11699 WOODARD - 11702 BEARPEN
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- MEDIUM
- POI Substation
- Woodward
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Ringtail Ridge Storage growth signals — PPAs, construction, new projects
Data-driven briefing on Prairie Ridge (Gas - CC) — fleet, generation, financial, and news signals.
TOCE TX BESS 2
Cross-dimensional entity briefing with KPIs, news intelligence, and fleet analysis.
Texas energy overview
Summary analysis with parallel narrative sections and visualizations.
Buffalo Prairie Storage queue pipeline — 1 projects by technology and status
Data-driven briefing on Prairie Ridge (Gas - CC) — fleet, generation, financial, and news signals.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.