Lightcycle Energy Storage
409.69 MW hybrid in Fayette, TX · In queue since January 2026 · Proposed COD March 2030
409.69 MW
Capacity
0
Components
10 months
In Queue
—
IA Status
COD target: 2030
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Total Duration
4y 2m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2030-03-01
Projected COD moved
1 time
May 2029 → Mar 2030
Net change
+10 months
first report to latest
Capacity
410 MW
unchanged in the reports
Latest stage
Screening started
in ERCOT's latest report
Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).
Cross-source intelligence
Experimental assessment saved at the research date. See the queue record for reported project facts.
Research sources and reasoning (5 recorded sources)
low confidence at research time
- interconnection.fyi/project/ercot-29inr0249
- infrasure.ai/project/ercot-29inr0249-lightcycle-energy-storage
- quicksandcheck.com/texas/fayette-county/
- ercotqueue.com/project/29INR0249
- ercotqueue.com/developer/lightcycle-energy-storage-llc
Commercial operation date: No press release, news item, or developer statement gives a COD. Quicksandcheck and interconnection.fyi repeat the LBNL date of Mar 2030. One Infrasure page shows May 2029 and another shows 2029, but those are queue aggregators, not financing-backed developer targets, so they do not override the filing. That 1-year gap would be minor anyway.
Developer: Every source names Lightcycle Energy Storage LLC, and all of them trace back to the queue filing. No parent, sponsor, or operating company has been identified, so it may be a shell entity whose backer is unknown.
Status: LBNL, ercotqueue.com, interconnection.fyi, and Quicksandcheck all list the project as active or in study, with no IA. Nothing indicates withdrawal or advancement beyond the study phase.
About
Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
Lightcycle Energy Storage is a proposed hybrid energy project in Fayette County, Texas, being developed by Lightcycle Energy Storage LLC. The project, identified as ERCOT-29INR0249 in the ERCOT interconnection queue, consists of 409.69 MW of battery energy storage. The project entered the queue on January 13, 2026, and has a proposed commercial operation date of May 1, 2029.
The project is currently listed as active in the ERCOT queue. The point of interconnection is the 9042 Winchester 345 kV substation. The project has appeared in recent news coverage.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- ERCOT queue source as of: Oct 1, 2026.
- Queue history observations through: Sep 2026.
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Fayette
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Lightcycle Energy Storage LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
9073 HOLMAN 345 kV
Data Source
Live · ERCOT
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_SOUTH
- Hub Confidence
- MEDIUM
- POI Substation
- Holman Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
TOCE TX BESS 2
Cross-dimensional entity briefing with KPIs, news intelligence, and fleet analysis.
Texas energy overview
Summary analysis with parallel narrative sections and visualizations.
State-by-state breakdown for ERCOT (Texas)
Summary analysis with parallel narrative sections and visualizations.
Queue projects in Texas
Data tables and metrics from the InfraSure database.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.