Two Step Solar
405.18 MW generation in Ellis, TX · In queue since December 2025 · Proposed COD September 2029
405.18 MW
Capacity
1
Components
Solar
11 months
In Queue
Facility Study
IA Phase
COD target: 2029
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Total Duration
3y 9m
Interconnection request submitted to ISO/RTO
SS Completed, FIS Started, No IA
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2029-09-17
Projected COD moved
1 time
Aug 2029 → Sep 2029
Net change
+1 months
first report to latest
Capacity
405 → 402 MW
changed in the reports
Latest stage
Screening started
in ERCOT's latest report
Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).
From dated articles. These observations may describe earlier stages or other project phases; see the queue record above for reported filing status.
Cross-source intelligence
Experimental assessment saved at the research date. See the queue record for reported project facts.
Research sources and reasoning (3 recorded sources)
low confidence at research time
- interconnection.fyi/project/ercot-29inr0196
- cleanview.co/power-projects/planned/solar-farms/texas/29INR0196/two-step-solar
- infrasure.ai/project/ercot-29inr0196-two-step-solar
Commercial operation date: Only queue-derived sources (LBNL snapshot and aggregators such as interconnection.fyi and cleanview, which mirror the queue) give a COD of Sept 2029 / 2029. No independent news or press release gives a different date.
Developer: The news-extracted developer (Flint Hills Resources) refers to a 30 MW refinery solar installation in Corpus Christi, which is a different project from this 405 MW Ellis County queue entry, so it was not applied. Only the LBNL filing entity, mirrored by aggregators, identifies the developer.
Status: LBNL lists the project as active with a Facility Study IA status, and aggregators (interconnection.fyi, cleanview) agree it is planned/active. No evidence of withdrawal or construction.
About
Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
Two Step Solar is a proposed 402.06 MW solar generation project located in Ellis County, Texas. The project, under development by Two Step Solar, LLC, consists of photovoltaic solar technology. It is currently active in the ERCOT interconnection queue as entry ERCOT-29INR0196, with a queue entry date of December 17, 2025, and a proposed commercial operation date of September 17, 2029. The point of interconnection is Tap 345kV 1907 Venus - 68091 Navarro.
The Two Step Solar project has been the subject of recent news coverage, with two articles categorized as pertaining to industry and regulatory matters.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- ERCOT queue source as of: Oct 1, 2026.
- Queue history observations through: Sep 2026.
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Ellis
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Two Step Solar, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
NAVARRO to VENUS_N5
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Last updated 2026-03-26
View all articlesTOCE TX BESS 2
Cross-dimensional entity briefing with KPIs, news intelligence, and fleet analysis.
Solar queue pipeline by status
Data tables and metrics from the InfraSure database.
Texas energy overview
Summary analysis with parallel narrative sections and visualizations.
State-by-state breakdown for ERCOT (Texas)
Summary analysis with parallel narrative sections and visualizations.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.