Two Step Solar
405.18 MW generation in Ellis, TX · In queue since December 2025 · Proposed COD September 2029
405.18 MW
Capacity
1
Components
Solar
7 months
In Queue
Facility Study
IA Phase
COD target: 2029
Total Duration
3y 9m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2029-09-17
Entered ERCOT interconnection queue, Facility Study phase
Two Step Solar is a proposed 402.06 MW solar generation project located in Ellis County, Texas. The project, under development by Two Step Solar, LLC, consists of photovoltaic solar technology. It is currently active in the ERCOT interconnection queue as entry ERCOT-29INR0196, with a queue entry date of December 17, 2025, and a proposed commercial operation date of September 17, 2029. The point of interconnection is Tap 345kV 1907 Venus - 68091 Navarro.
The Two Step Solar project has been the subject of recent news coverage, with two articles categorized as pertaining to industry and regulatory matters.
Generated from interconnection queue and public data sources
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Ellis
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Two Step Solar, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
NAVARRO to VENUS_N5
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- MEDIUM
- Nearest Node (Estimated)
- DSWL_BES1
- POI Substation
- Venus Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.