Gridline Solar (ERCOT-29INR0184) — Project Summary

Queue ID
ERCOT-29INR0184
Capacity
400 MW
Technology
Solar
Status
active
Location
Crockett, TX
Region
ERCOT
Developer
Big Lake Ranch LLC
IA Status
Facility Study

Gridline Solar

ERCOT-29INR0184BetaActiveSolarERCOTLBNL + Live

400 MW generation in Crockett, TX · In queue since August 2025 · Proposed COD July 2029

BA: ERCOISO/RTO: ERCOTNERC: TRERC: ERCOT

400 MW

Capacity

1

Components

Solar

1y 3m

In Queue

Facility Study

IA Phase

COD target: 2029

Asset Intelligence Map

One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.

5 live dimensions
4 decision models

Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.

Structured from the current asset record; empty data branches are omitted.Locked nodes are InfraSure decision models; no simulated values shown.
Interconnection

Total Duration

3y 11m

Facilities Study50%
Queue EntryAug 18, 2025

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

SS Completed, FIS Started, No IA

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2029-07-01

Queue history
29INR0184 · 15 monthly ERCOT reports, Jul 2025 – Sep 2026

Projected COD moved

0 times

Jul 2029 → Jul 2029

Net change

0 months

first report to latest

Capacity

400 MW

unchanged in the reports

Latest stage

Screening started

in ERCOT's latest report

Projected COD in each reportDue now (report date = COD)Milestone first reported
Screening study startedAug 18, 2025

Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).

Cross-source intelligence

Saved research · Beta
Researched Oct 25, 2026

Experimental assessment saved at the research date. See the queue record for reported project facts.

Research COD
Jul 1, 2029
From queue filing
Developer in saved assessment
Big Lake Ranch LLC
From queue filing
Status at research time
Active
Active in the ERCOT queue at the Facility Study stage, with no IA executed. No construction, permitting, or offtake news found.
Financing
Not recorded
Research sources and reasoning (3 recorded sources)

low confidence at research time

  1. cleanview.co/power-projects/planned/solar-farms/texas/29INR0184/gridline-solar
  2. infrasure.ai/project/ercot-29inr0184-gridline-solar
  3. interconnection.fyi/project/ercot-29inr0184

Commercial operation date: Only the LBNL proposed COD (2029-07-01) is available. Cleanview's 'Expected online 2029' matches it but is an aggregator that likely republishes the queue data, so it is not an independent signal. No developer press release or news gives a financing-backed target.

Developer: Infrasure repeats Big Lake Ranch LLC as the developer, but it appears to draw on the same queue data. No parent or operating company was found in any search result. The name is probably a project shell, but this is unconfirmed.

Status: LBNL and interconnection.fyi both show the project as active. The interxdata listing of 'operational' conflicts with the August 2025 queue entry and the Facility Study status, so it is treated as a data error.

About

Saved background

Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source

Figures and claims below reflect the saved summary. See the queue record for reported project facts.

Gridline Solar is a proposed 400 MW solar photovoltaic generation project located in Crockett County, Texas. The project, developed by Big Lake Ranch LLC, is in the ERCOT interconnection queue as entry ERCOT-29INR0184, with a queue entry date of August 18, 2025. The proposed commercial operation date is July 1, 2029, at the point of interconnection 76005 Schneeman Draw LCRA.

The Gridline Solar project has been mentioned in recent news coverage related to the electric grid and the energy industry.

Summary provenance

Summary generated Apr 10, 2026 (UTC).

Source dates used by this summary were not recorded.

Dates in the current asset record

These may postdate the saved summary; they do not establish which inputs it used.

  • ERCOT queue source as of: Oct 1, 2026.
  • Queue history observations through: Sep 2026.
Development Risk

Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.

Available on the InfraSure platform

See the full development-risk decomposition for this project.

P(COD by stated date)
Withdrawal probability vs cohort
IA cluster risk
Project Details

State

TX

County

Crockett

Grid Region

ERCOT (Texas)

Market

ISO/RTO Member

Developer

Big Lake Ranch LLC

Utility

—

Entity

ERCOT

Service Type

—

Point of Interconnection

76005 Schneeman Draw LCRA

Data Source

LBNL + Live

Risk Analytics

Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.

Available on the InfraSure platform

See the full risk decomposition + scenarios for this project.

Climate hazards (8+)
Generation variability (P10/P50/P90)
Offtake + transmission counterparty
Generation Forecast

Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.

Available on the InfraSure platform

See the full forecast + scenario decomposition for this project.

P50 conditioned on COD
Capacity factor vs cohort
Weather + policy scenarios
Financial Forecast

Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.

Available on the InfraSure platform

See the full revenue + DSCR projection for this project.

Revenue conditioned on COD
Financing close risk
Cohort DSCR comparison
Market Context
Approximate
ISO / RTO
ERCOT
Trading Hub
HB_WEST
Hub Confidence
LOW

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

Insights & Articles (1)Beta

Last updated 2026-03-26

View all articles
InfraSure platform

Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.