Glass Mountain Solar Solstice
304 MW generation in Pecos, TX · In queue since September 2025 · Proposed COD October 2029
304 MW
Capacity
1
Components
Solar
1y 2m
In Queue
Facility Study
IA Phase
COD target: 2029
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Total Duration
4y 1m
Interconnection request submitted to ISO/RTO
SS Completed, FIS Started, No IA
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2029-10-20
Projected COD moved
2 times
Mar 2029 → Oct 2029
Net change
+7 months
first report to latest
Capacity
304 → 302 MW
changed in the reports
Latest stage
Screening started
in ERCOT's latest report
Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).
Cross-source intelligence
Experimental assessment saved at the research date. See the queue record for reported project facts.
Research sources and reasoning (3 recorded sources)
low confidence at research time
- glassmountainenergy.com/
- interconnection.fyi/project/ercot-29inr0181
- infrasure.ai/project/ercot-29inr0181-glass-mountain-solar-solstice
Commercial operation date: The LBNL proposed COD of 2029-10-20 is consistent with the Apex Clean Energy Glass Mountain Energy page, which lists the 800 MW hybrid project (500 MW wind + 300 MW solar) as 2029. interconnection.fyi's October 19, 2029 date comes from the same queue data, so it is not independent. No newer COD target was found.
Developer: Apex's Glass Mountain Energy page describes a 300 MW solar component in Pecos County, TX targeting 2029, which matches this 304 MW project and the 'Glass Mountain Solar, LLC' filer. No source states that the LLC is an Apex entity, so this link is inferred from the name, location, size and timing.
Status: LBNL lists the project as active (Facility Study, IA date null). Search results show only queue listings and a developer project page, with nothing indicating withdrawal or construction.
About
Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
The Glass Mountain Solar Solstice project is a proposed 304 MW solar generation project located in Pecos County, Texas. Developed by Glass Mountain Solar, LLC, the project consists of photovoltaic solar technology. It is listed in the ERCOT interconnection queue as entry ERCOT-29INR0181, with a queue entry date of September 22, 2025.
The proposed commercial operation date (COD) for the Glass Mountain Solar Solstice project is October 20, 2029. The point of interconnection (POI) is the 60404 SOLSTICE 345 kV substation. The project is currently listed as active in the interconnection queue.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- ERCOT queue source as of: Oct 1, 2026.
- Queue history observations through: Sep 2026.
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Pecos
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Glass Mountain Solar, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
60404 SOLSTICE 345 kV
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_WEST
- Hub Confidence
- MEDIUM
- Nearest Node (Estimated)
- HOVEY_GEN
- POI Substation
- Solstice Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
TOCE TX BESS 2
Cross-dimensional entity briefing with KPIs, news intelligence, and fleet analysis.
Texas energy overview
Summary analysis with parallel narrative sections and visualizations.
State-by-state breakdown for ERCOT (Texas)
Summary analysis with parallel narrative sections and visualizations.
Glass Mountain Solar Solstice
Data-driven briefing on Glass Mountain Solar Solstice — fleet, generation, financial, and news signals.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.