Tolar Energy Center
1,252 MW generation in Hood, TX · In queue since September 2025 · Proposed COD November 2029
1,252 MW
Capacity
1
Components
Gas
1y 2m
In Queue
Facility Study
IA Phase
COD target: 2029
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Total Duration
4y 2m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2029-11-01
Projected COD moved
1 time
Nov 2029 → Jun 2030
Net change
+7 months
first report to latest
Capacity
1252 MW
unchanged in the reports
Latest stage
Cancelled
last listed May 2026
Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).
From dated articles. These observations may describe earlier stages or other project phases; see the queue record above for reported filing status.
Cross-source intelligence
Experimental assessment saved at the research date. Research and queue COD differ; this comparison does not confirm either date. See the queue record for reported project facts.
Milestones in this assessment
NRG withdrew its air permit application for the proposed Hood County gas plant amid community opposition (the permit application, not the queue entry).
kera.orgResearch sources and reasoning (6 recorded sources)
medium confidence at research time
- kera.org/2026/06/25/nrg-withdraws-permit-for-proposed-tolar-gas-plant-amid-community-opposition/
- star-telegram.com/news/local/article316239676.html
- cleanview.co/power-projects/planned/natural-gas-power-plants/texas/29INR0180/tolar-energy-center
- infrasure.ai/project/ercot-29inr0180-tolar-energy-center
- gem.wiki/NRG_Tolar_Power_Center
- businesswire.com/news/home/20250225753165/en/NRG-Energy-GE-Vernova-and-Kiewit-Accelerating-New-Generation-Capacity-to-Support-Demand-Growth
Commercial operation date: Cleanview lists the project as "Expected online 2030" and Infrasure shows a proposed COD of 2030-06-10, against LBNL's 2029-11-01. The shift is only about 7 months. Infrasure's own text also still quotes Nov 2029, so the year is the most reliable part.
Developer: The LBNL filing entity NRG Tolar Power LLC is a project LLC. News coverage names NRG Energy as the operating parent, including the Business Wire release with GE Vernova and Kiewit and the KERA report on NRG's permit withdrawal.
Status: LBNL shows the queue entry as active, and no source reports it withdrawn from the queue. The June 2026 air permit withdrawal (KERA) is a real setback that raises realization risk, but it does not by itself end the queue position.
About
Generated Apr 10, 2026 · Predates May 2026 queue source
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
The Tolar Energy Center is a proposed 1252 MW gas-fired combined-cycle generation project located in Hood County, Texas. Developed by NRG Tolar Power LLC, the project is currently active in the ERCOT interconnection queue as entry ERCOT-29INR0180, with a queue entry date of September 22, 2025. The proposed commercial operation date is November 1, 2029. The point of interconnection is Tap 345 KV circuit 1 from 1440 Comanche Switch to 1900 Comanche Peak SES.
The Tolar Energy Center development has been the subject of recent news coverage, with four articles appearing in industry and deals publications.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- LBNL queue source as of: Dec 31, 2025.
- Queue history observations through: May 2026.
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Hood
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
NRG Tolar Power LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 345 KV circuit 1 from 1440 Comanche Switch to 1900 Comanche Peak SES.
Data Source
LBNL
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_SOUTH
- Hub Confidence
- MEDIUM
- POI Substation
- 1
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Last updated 2026-04-09
View all articlesTOCE TX BESS 2
Cross-dimensional entity briefing with KPIs, news intelligence, and fleet analysis.
Texas energy overview
Summary analysis with parallel narrative sections and visualizations.
State-by-state breakdown for ERCOT (Texas)
Summary analysis with parallel narrative sections and visualizations.
Geothermal queue pipeline overview
Summary analysis with parallel narrative sections and visualizations.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.