Tolar Energy Center (ERCOT-29INR0180) — Project Summary

Queue ID
ERCOT-29INR0180
Capacity
1252 MW
Technology
Gas
Status
active
Location
Hood, TX
Region
ERCOT
Developer
NRG Tolar Power LLC
IA Status
Facility Study

Tolar Energy Center

ERCOT-29INR0180BetaActiveGasERCOTLBNL

1,252 MW generation in Hood, TX · In queue since September 2025 · Proposed COD November 2029

BA: ERCOISO/RTO: ERCOTNERC: TRERC: ERCOT

1,252 MW

Capacity

1

Components

Gas

1y 2m

In Queue

Facility Study

IA Phase

COD target: 2029

Asset Intelligence Map

One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.

5 live dimensions
4 decision models

Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.

Structured from the current asset record; empty data branches are omitted.Locked nodes are InfraSure decision models; no simulated values shown.
Interconnection

Total Duration

4y 2m

Facilities Study50%
Queue EntrySep 22, 2025

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2029-11-01

Queue history
29INR0180 · 9 monthly ERCOT reports, Sep 2025 – May 2026

Projected COD moved

1 time

Nov 2029 → Jun 2030

Net change

+7 months

first report to latest

Capacity

1252 MW

unchanged in the reports

Latest stage

Cancelled

last listed May 2026

Projected COD in each reportDue now (report date = COD)Milestone first reported
Screening study startedSep 22, 2025
CancelledJun 25, 2026

Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).

News-reported activity
as of 21 months ago

From dated articles. These observations may describe earlier stages or other project phases; see the queue record above for reported filing status.

Latest activitypartnershipBusiness Wire · 2025-02-26

Cross-source intelligence

Saved research · Beta
Researched Oct 25, 2026

Experimental assessment saved at the research date. Research and queue COD differ; this comparison does not confirm either date. See the queue record for reported project facts.

Research COD
2030
Differs from queue: Nov 1, 2029
Developer in saved assessment
NRG Energy
Filed as NRG Tolar Power LLC
Status at research time
Active
Active in the ERCOT queue (Facility Study, no IA executed), but NRG withdrew its air permit application in June 2026 amid local opposition. Global Energy Monitor lists it as pre-construction.
Financing
Not recorded

Milestones in this assessment

WithdrawnJun 2026Latest in this assessment

NRG withdrew its air permit application for the proposed Hood County gas plant amid community opposition (the permit application, not the queue entry).

kera.org
Research sources and reasoning (6 recorded sources)

medium confidence at research time

  1. kera.org/2026/06/25/nrg-withdraws-permit-for-proposed-tolar-gas-plant-amid-community-opposition/
  2. star-telegram.com/news/local/article316239676.html
  3. cleanview.co/power-projects/planned/natural-gas-power-plants/texas/29INR0180/tolar-energy-center
  4. infrasure.ai/project/ercot-29inr0180-tolar-energy-center
  5. gem.wiki/NRG_Tolar_Power_Center
  6. businesswire.com/news/home/20250225753165/en/NRG-Energy-GE-Vernova-and-Kiewit-Accelerating-New-Generation-Capacity-to-Support-Demand-Growth

Commercial operation date: Cleanview lists the project as "Expected online 2030" and Infrasure shows a proposed COD of 2030-06-10, against LBNL's 2029-11-01. The shift is only about 7 months. Infrasure's own text also still quotes Nov 2029, so the year is the most reliable part.

Developer: The LBNL filing entity NRG Tolar Power LLC is a project LLC. News coverage names NRG Energy as the operating parent, including the Business Wire release with GE Vernova and Kiewit and the KERA report on NRG's permit withdrawal.

Status: LBNL shows the queue entry as active, and no source reports it withdrawn from the queue. The June 2026 air permit withdrawal (KERA) is a real setback that raises realization risk, but it does not by itself end the queue position.

About

Saved background

Generated Apr 10, 2026 · Predates May 2026 queue source

Figures and claims below reflect the saved summary. See the queue record for reported project facts.

The Tolar Energy Center is a proposed 1252 MW gas-fired combined-cycle generation project located in Hood County, Texas. Developed by NRG Tolar Power LLC, the project is currently active in the ERCOT interconnection queue as entry ERCOT-29INR0180, with a queue entry date of September 22, 2025. The proposed commercial operation date is November 1, 2029. The point of interconnection is Tap 345 KV circuit 1 from 1440 Comanche Switch to 1900 Comanche Peak SES.

The Tolar Energy Center development has been the subject of recent news coverage, with four articles appearing in industry and deals publications.

Summary provenance

Summary generated Apr 10, 2026 (UTC).

Source dates used by this summary were not recorded.

Dates in the current asset record

These may postdate the saved summary; they do not establish which inputs it used.

  • LBNL queue source as of: Dec 31, 2025.
  • Queue history observations through: May 2026.
Development Risk

Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.

Available on the InfraSure platform

See the full development-risk decomposition for this project.

P(COD by stated date)
Withdrawal probability vs cohort
IA cluster risk
Project Details

State

TX

County

Hood

Grid Region

ERCOT (Texas)

Market

ISO/RTO Member

Developer

NRG Tolar Power LLC

Utility

—

Entity

ERCOT

Service Type

—

Point of Interconnection

Tap 345 KV circuit 1 from 1440 Comanche Switch to 1900 Comanche Peak SES.

Data Source

LBNL

PartnerGE Vernova and KiewitBusiness Wire · 2025-02-26
CompanyNRG EnergyBusiness Wire · 2025-02-26
RulingNoticeHood County News · 2024-09-12
Risk Analytics

Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.

Available on the InfraSure platform

See the full risk decomposition + scenarios for this project.

Climate hazards (8+)
Generation variability (P10/P50/P90)
Offtake + transmission counterparty
Generation Forecast

Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.

Available on the InfraSure platform

See the full forecast + scenario decomposition for this project.

P50 conditioned on COD
Capacity factor vs cohort
Weather + policy scenarios
Financial Forecast

Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.

Available on the InfraSure platform

See the full revenue + DSCR projection for this project.

Revenue conditioned on COD
Financing close risk
Cohort DSCR comparison
Market Context
Approximate
ISO / RTO
ERCOT
Trading Hub
HB_SOUTH
Hub Confidence
MEDIUM
POI Substation
1

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

Insights & Articles (2)Beta

Last updated 2026-04-09