Meitner 2 Wind (ERCOT-29INR0103) — Project Summary

Queue ID
ERCOT-29INR0103
Capacity
709.1 MW
Technology
Wind
Status
active
Location
Gray, TX
Region
ERCOT
Developer
IP Meitner, LLC
IA Status
Facility Study

Meitner 2 Wind

ERCOT-29INR0103BetaActiveWindERCOTLBNL + Live

709.1 MW generation in Gray, TX · In queue since June 2025 · Proposed COD June 2028

BA: ERCOISO/RTO: ERCOTNERC: TRERC: ERCOT

709.1 MW

Capacity

1

Components

Wind

1y 5m

In Queue

Facility Study

IA Phase

COD target: 2028

Asset Intelligence Map

One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.

5 live dimensions
4 decision models

Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.

Structured from the current asset record; empty data branches are omitted.Locked nodes are InfraSure decision models; no simulated values shown.
Interconnection

Total Duration

3 years

Facilities Study50%
Queue EntryJun 5, 2025

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

SS Completed, FIS Started, No IA

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2028-06-30

Queue history
29INR0103 · 17 monthly ERCOT reports, May 2025 – Sep 2026

Projected COD moved

0 times

Jun 2028 → Jun 2028

Net change

0 months

first report to latest

Capacity

709 MW

unchanged in the reports

Latest stage

Screening started

in ERCOT's latest report

Projected COD in each reportDue now (report date = COD)Milestone first reported
Screening study startedJun 5, 2025

Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).

Cross-source intelligence

Saved research · Beta
Researched Oct 25, 2026

Experimental assessment saved at the research date. See the queue record for reported project facts.

Research COD
Jun 30, 2028
Developer in saved assessment
Intersect (Google/Alphabet)
Ownership change in saved research
Status at research time
Active
Active in the ERCOT queue at Facility Study with no IA executed. The broader Meitner Energy Center (data center plus 1 GW+ wind, solar and storage) has been launched, with construction reported as initiated.
Financing
Not recorded
Ownership history
  1. —·Intersect Power (independent)→Intersect (acquired by Google/Alphabet)latitudemedia.com

Milestones in this assessment

COD target2028Latest in this assessment

Local coverage says Meitner Energy Center completion is expected by 2028.

abc7amarillo.com
Research sources and reasoning (5 recorded sources)

medium confidence at research time

  1. latitudemedia.com/news/google-and-intersect-to-build-first-post-acquisition-project-in-texas/
  2. powermag.com/google-launches-1-gw-plus-co-located-data-center-and-generation-complex-in-texas-panhandle/
  3. abc7amarillo.com/news/local/meitner-energy-center-in-gray-county-aims-for-jobs-growth-completion-expected-by-2028-google-pampa-chamber-of-commerce-cortnie-hale-texas-water-impact-fund-data-center
  4. infrasure.ai/project/ercot-29inr0103-meitner-2-wind
  5. ercotqueue.com/project/29INR0103

Commercial operation date: LBNL proposes 2028-06-30. KVII's coverage of the Meitner Energy Center in Gray County says 'completion expected by 2028', which is consistent. Aggregators (infrasure, cleanview) repeat the LBNL date, so they are not independent confirmation.

Developer: 'IP Meitner, LLC' appears to be the project shell for Intersect (Power), which is developing the Meitner Energy Center with Google. Latitude Media calls it the first post-acquisition Google/Intersect project in Texas. The link between the 'Meitner 2 Wind' queue entry and the Meitner Energy Center is inferred from the name and the Gray County location.

Status: LBNL shows active with a Facility Study IA status, and ercotqueue.com confirms there is no IA yet. The campus-level construction news does not show that this specific 709 MW wind queue entry has moved past the study phase.

About

Saved background

Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source

Figures and claims below reflect the saved summary. See the queue record for reported project facts.

The Meitner 2 Wind project is a proposed 709.1 MW wind generation facility in Gray County, Texas. The project, developed by IP Meitner, LLC, is currently active in the ERCOT interconnection queue as entry ERCOT-29INR0103, with a queue entry date of June 5, 2025. The proposed commercial operation date is June 30, 2028, and the point of interconnection is the 79000 Gray Substation at 345kV.

The project consists of wind turbine technology. It is listed in the ERCOT queue and has appeared in recent news coverage regarding renewable energy development in Texas.

Summary provenance

Summary generated Apr 10, 2026 (UTC).

Source dates used by this summary were not recorded.

Dates in the current asset record

These may postdate the saved summary; they do not establish which inputs it used.

  • ERCOT queue source as of: Oct 1, 2026.
  • Queue history observations through: Sep 2026.
Development Risk

Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.

Available on the InfraSure platform

See the full development-risk decomposition for this project.

P(COD by stated date)
Withdrawal probability vs cohort
IA cluster risk
Project Details

State

TX

County

Gray

Grid Region

ERCOT (Texas)

Market

ISO/RTO Member

Developer

IP Meitner, LLC

Utility

—

Entity

ERCOT

Service Type

—

Point of Interconnection

79000 Gray Substation 345kV

Data Source

LBNL + Live

Risk Analytics

Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.

Available on the InfraSure platform

See the full risk decomposition + scenarios for this project.

Climate hazards (8+)
Generation variability (P10/P50/P90)
Offtake + transmission counterparty
Generation Forecast

Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.

Available on the InfraSure platform

See the full forecast + scenario decomposition for this project.

P50 conditioned on COD
Capacity factor vs cohort
Weather + policy scenarios
Financial Forecast

Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.

Available on the InfraSure platform

See the full revenue + DSCR projection for this project.

Revenue conditioned on COD
Financing close risk
Cohort DSCR comparison
Market Context
Approximate
ISO / RTO
ERCOT
Trading Hub
HB_WEST
Hub Confidence
MEDIUM
POI Substation
Gray Substation

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No insights available for this project.
InfraSure platform

Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.