Aurelius 2 Solar
445.4 MW generation in Deaf Smith, TX · In queue since December 2023 · Proposed COD September 2028
445.4 MW
Capacity
1
Components
Solar
2y 11m
In Queue
Facility Study
IA Phase
COD target: 2028
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Total Duration
4y 9m
Interconnection request submitted to ISO/RTO
SS Completed, FIS Started, IA
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-09-30
Projected COD moved
0 times
Sep 2028 → Sep 2028
Net change
0 months
first report to latest
Capacity
445 MW
unchanged in the reports
Latest stage
IA signed
in ERCOT's latest report
Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).
Cross-source intelligence
Experimental assessment saved at the research date. See the queue record for reported project facts.
Research sources and reasoning (7 recorded sources)
low confidence at research time
- cleanview.co/power-projects/planned/solar-farms/texas/29INR0009/aurelius-2-solar
- aterio.io/insights/us-power-generation/ep/aurelius-64766
- interchange.puc.texas.gov/search/filings/?UtilityType=A&ControlNumber=35077&ItemMatch=Equal&DocumentType=ALL&SortBy=FileStamp&SortOrder=Descending
- ercotqueue.com/project/29INR0009
- ercotqueue.com/developer/ip-roman-llc
- groundtrace.io/projects/caliche-mound-solar-pwdskel4wyvwm
- txdatacenterwatch.com/project/google-roman-deafsmith/
Commercial operation date: The only COD signal is the LBNL/ERCOT queue date of 2028-09-30. Cleanview ("expected to come online in September 2028") and Aterio ("Activation ~Sep 29 2028") appear to mirror the queue data, so they are not independent confirmation. No developer press release or news item gives a financing-backed target.
Developer: Every source (ERCOT queue trackers, the PUC SGIA filing, the Texas data center watch page) names IP Roman, LLC as the developer. None names a parent company. The 'IP' prefix and the link to the Google-operated 'Project Roman' data center suggest an Intersect Power affiliation, but the snippets don't state it, so I did not assert a parent.
Status: LBNL says active and the trackers agree. The PUC filing hints at progress on the interconnection agreement, but its execution date is unclear, so I did not upgrade the status to IA Executed.
About
Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
The Aurelius 2 Solar project is a proposed solar generation facility with a total capacity of 445.4 MW. Located in Deaf Smith County, Texas, the project is being developed by IP Roman II, LLC. It is currently active in the ERCOT interconnection queue as entry ERCOT-29INR0009, with a queue entry date of December 4, 2023. The proposed commercial operation date is September 30, 2028, and the project's interconnection agreement status is currently in the Facility Study phase.
The point of interconnection is the 23908 Deaf Smith station 345 kV. This interconnection request includes a 600 MW private use network (PUN) load at the medium voltage side of the Main Power Transformers (MPTs) for a total of 1800 MW PUN load. The project has appeared in recent news coverage regarding renewable energy development in Texas.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- ERCOT queue source as of: Oct 1, 2026.
- Queue history observations through: Sep 2026.
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Deaf Smith
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
IP Roman, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
23908 Deaf Smith station 345 kV. This INR has a 600 MW PUN load at the medium voltage side of the MPTs for a total of 1800 MW PUN load (refer to the substation SLD).
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_WEST
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Aurelius 2 Solar
Data-driven briefing on Aurelius 2 Solar — fleet, generation, financial, and news signals.
TOCE TX BESS 2
Cross-dimensional entity briefing with KPIs, news intelligence, and fleet analysis.
Solar queue pipeline by status
Data tables and metrics from the InfraSure database.
Texas energy overview
Summary analysis with parallel narrative sections and visualizations.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.