Berryman Road Storage
155 MW storage in Archer, TX · In queue since June 2025 · Proposed COD April 2029
155 MW
Capacity
1
Components
Battery
1y 5m
In Queue
Facility Study
IA Phase
COD target: 2029
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Total Duration
3y 10m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2029-04-16
Projected COD moved
4 times
May 2028 → Sep 2029
Net change
+16 months
first report to latest
Capacity
254 → 150 MW
changed in the reports
Latest stage
Cancelled
last listed Jun 2026
Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).
Cross-source intelligence
Experimental assessment saved at the research date. Research and queue COD differ; this comparison does not confirm either date. See the queue record for reported project facts.
Milestones in this assessment
Entered ERCOT queue for Facility Study phase
Research sources and reasoning (0 recorded sources)
low confidence at research time
No source list recorded with this assessment.
Commercial operation date: Only LBNL queue data available showing proposed COD of August 2031. No independent news or research sources found to validate or contradict this timeline.
Developer: LBNL filing entity 'Horizon Energy Storage Greenfield Project Holdings LLC' is a project-specific holding company structure. Parent operating company is Horizon Energy Storage.
Status: LBNL shows Active status in Facility Study phase with no IA executed. Long timeline to 2031 COD suggests early interconnection queue position with substantial development runway ahead.
About
Generated Apr 10, 2026 · Predates Jun 2026 queue source
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
The Berryman Road Storage project is a proposed 154.09 MW hybrid development in Archer County, Texas. The project, being developed by Horizon Energy Storage Greenfield Project Holdings LLC, consists of battery energy storage. It is currently active in the ERCOT interconnection queue as entry ERCOT-28INR0373, with a queue entry date of June 5, 2025, and a proposed commercial operation date of April 16, 2029.
The point of interconnection for the project is Tap 138kV 1424# Bowman Substation - 11525# Short grass Substation.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- LBNL queue source as of: Dec 31, 2025.
- Queue history observations through: Jun 2026.
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Archer
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Horizon Energy Storage Greenfield Project Holdings LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 138kV 1424# Bowman Substation - 11525# Short grass Substation
Data Source
LBNL
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- MEDIUM
- POI Substation
- Bowman Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.